Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package II

Project KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package II
Project Code ALPKIIFB0619496P3
Type Package
Main Project KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description Construction of 16LL OHSR at Chudukadu ,Construction of 12LL OHSR at Chandanakkavu in Alappuzha Municipality
Status On-going
District Alappuzha
Executing Office KIIFB Projects (ALP)
Agreement Number
Agreement Date
TS Amount (Rs) 122600000
TS Number WRD/KWA-CE(CR)/EST_TS/534/2022_5_1_1
Technical specification Construction of 16LL OHSR at Chudukadu ,Construction of 12LL OHSR at Chandanakkavu and Construction of 6LL OHSR at Vazhichery in Alappuzha Municipality

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 26/07/2021
Scheduled date of Completion as per agreement 13 Mar 2024
Expected date of Completion 13/03/2024

Processing Dates

TS Date 03 Oct 2022
Estimate Approval 03 Oct 2022
NIT Approval 01 Nov 2022
Tender Closing 10 Apr 2023
Technichal Pre-Qualification 11 Apr 2023
Price bid opening 11 Apr 2023

Approval Dates

Workorder Date 16 Jun 2023
NA 21 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha KIIFB - AE 4
Date: 17/05/2024

Work in progress | 35% Completed

Chudukadu OHSR 16 LL - Pile concreting work completed. 75 nos /75. Pile chipping work- nos 75/75 nos completed. Raft slab , strip beam reinforcement work completed. Raft slab, Strip beam& pile cap concreting completed . Strip beam shuttering work completed. Strip beam concreting completed. Pedestal column concrete completed. Reinforcement work completed .Plinth beam concreting completed. Column concreting ground floor 42 nos. completed. First brace beam concreting completed. Second stage column concreting 42 nos completed. Shuttering& steel work for second brace beam completed. Second brace beam concreting completed. Column concreting SF completed. Shuteering and steel work for third brace beam completed . Third brace beam concreting completed. Fourth stage column concreting completed. Fourth brace beam steel work & shuttering wok progressing. Chandanakkavu OHSR 12LL - site levelling work completed. Test pile completed. Test pile loading work completed. PCC work completed .Test pile 1 no. W.Pile 56/56 nos completed. Pile load test completed. Pile chipping work 56/56nos completed. Trench levelling work for PCC started. PCC work completed. Steel work for raft slab progressing. Raft slab concreting completed. Strip beam concreting completed. Column concrete shuttering and steel work completed. Pedestal column concrete work progressing. Steel work for plinth beam completed. PCC below plinth beam completed. Plinth beam concreting completed. Column concreting GF completed. First brace beam shuttering & steel work completed. First brace beam concreting completed. FF column column concreting completed. Second brace beam steel and shuttering work is completed. Second brace beam concreting completed. Third stage column concreting completed. Third brace beam shuttering and steel work progressing..

Alappuzha KIIFB - AE 4
Date: 16/05/2024

Work in progress | 35% Completed

Chudukadu OHSR 16 LL - Pile concreting work completed. 75 nos /75. Pile chipping work- nos 75/75 nos completed. Raft slab , strip beam reinforcement work completed. Raft slab, Strip beam& pile cap concreting completed . Strip beam shuttering work completed. Strip beam concreting completed. Pedestal column concrete completed. Reinforcement work completed .Plinth beam concreting completed. Column concreting ground floor 42 nos. completed. First brace beam concreting completed. Second stage column concreting 42 nos completed. Shuttering& steel work for second brace beam completed. Second brace beam concreting completed. Column concreting SF completed. Shuteering and steel work for third brace beam completed . Third brace beam concreting completed. Fourth stage column concreting completed. Fourth brace beam steel work & shuttering wok progressing. Chandanakkavu OHSR 12LL - site levelling work completed. Test pile completed. Test pile loading work completed. PCC work completed .Test pile 1 no. W.Pile 56/56 nos completed. Pile load test completed. Pile chipping work 56/56nos completed. Trench levelling work for PCC started. PCC work completed. Steel work for raft slab progressing. Raft slab concreting completed. Strip beam concreting completed. Column concrete shuttering and steel work completed. Pedestal column concrete work progressing. Steel work for plinth beam completed. PCC below plinth beam completed. Plinth beam concreting completed. Column concreting GF completed. First brace beam shuttering & steel work completed. First brace beam concreting completed. FF column column concreting completed. Second brace beam steel and shuttering work is completed. Second brace beam concreting completed. Third stage column concreting completed. Third brace beam shuttering and steel work progressing..