KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package II
Project |
KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package II |
Project Code |
ALPKIIFB0619496P3 |
Type |
Package |
Main Project |
KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths
|
Funding Agency |
KIIFB |
Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Construction of 16LL OHSR at Chudukadu ,Construction of 12LL OHSR at Chandanakkavu in Alappuzha Municipality |
Status |
On-going |
District |
Alappuzha |
Executing Office |
KIIFB Projects (ALP) |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
122600000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/534/2022_5_1_1 |
Technical specification |
Construction of 16LL OHSR at Chudukadu ,Construction of 12LL OHSR at Chandanakkavu and Construction of 6LL OHSR at Vazhichery in Alappuzha Municipality |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
26/07/2021 |
Scheduled date of Completion as per agreement |
13 Mar 2024 |
Expected date of Completion |
13/03/2024 |
Processing Dates
TS Date |
03 Oct 2022 |
Estimate Approval |
03 Oct 2022 |
NIT Approval |
01 Nov 2022 |
Tender Closing |
10 Apr 2023 |
Technichal Pre-Qualification |
11 Apr 2023 |
Price bid opening |
11 Apr 2023 |
Approval Dates
Workorder Date |
16 Jun 2023 |
NA |
21 Jun 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Alappuzha KIIFB - AE 4 |
Date: 17/05/2024 |
Work in progress | 35% Completed
Chudukadu OHSR 16 LL - Pile concreting work completed. 75 nos /75. Pile chipping work- nos 75/75 nos completed. Raft slab , strip beam reinforcement work completed. Raft slab, Strip beam& pile cap concreting completed . Strip beam shuttering work completed. Strip beam concreting completed. Pedestal column concrete completed. Reinforcement work completed .Plinth beam concreting completed. Column concreting ground floor 42 nos. completed. First brace beam concreting completed. Second stage column concreting 42 nos completed. Shuttering& steel work for second brace beam completed. Second brace beam concreting completed. Column concreting SF completed. Shuteering and steel work for third brace beam completed . Third brace beam concreting completed. Fourth stage column concreting completed. Fourth brace beam steel work & shuttering wok progressing. Chandanakkavu OHSR 12LL - site levelling work completed. Test pile completed. Test pile loading work completed. PCC work completed .Test pile 1 no. W.Pile 56/56 nos completed. Pile load test completed. Pile chipping work 56/56nos completed. Trench levelling work for PCC started. PCC work completed. Steel work for raft slab progressing. Raft slab concreting completed. Strip beam concreting completed. Column concrete shuttering and steel work completed. Pedestal column concrete work progressing. Steel work for plinth beam completed. PCC below plinth beam completed. Plinth beam concreting completed. Column concreting GF completed. First brace beam shuttering & steel work completed. First brace beam concreting completed. FF column column concreting completed. Second brace beam steel and shuttering work is completed. Second brace beam concreting completed. Third stage column concreting completed. Third brace beam shuttering and steel work progressing..
Alappuzha KIIFB - AE 4 |
Date: 16/05/2024 |
Work in progress | 35% Completed
Chudukadu OHSR 16 LL - Pile concreting work completed. 75 nos /75. Pile chipping work- nos 75/75 nos completed. Raft slab , strip beam reinforcement work completed. Raft slab, Strip beam& pile cap concreting completed . Strip beam shuttering work completed. Strip beam concreting completed. Pedestal column concrete completed. Reinforcement work completed .Plinth beam concreting completed. Column concreting ground floor 42 nos. completed. First brace beam concreting completed. Second stage column concreting 42 nos completed. Shuttering& steel work for second brace beam completed. Second brace beam concreting completed. Column concreting SF completed. Shuteering and steel work for third brace beam completed . Third brace beam concreting completed. Fourth stage column concreting completed. Fourth brace beam steel work & shuttering wok progressing. Chandanakkavu OHSR 12LL - site levelling work completed. Test pile completed. Test pile loading work completed. PCC work completed .Test pile 1 no. W.Pile 56/56 nos completed. Pile load test completed. Pile chipping work 56/56nos completed. Trench levelling work for PCC started. PCC work completed. Steel work for raft slab progressing. Raft slab concreting completed. Strip beam concreting completed. Column concrete shuttering and steel work completed. Pedestal column concrete work progressing. Steel work for plinth beam completed. PCC below plinth beam completed. Plinth beam concreting completed. Column concreting GF completed. First brace beam shuttering & steel work completed. First brace beam concreting completed. FF column column concreting completed. Second brace beam steel and shuttering work is completed. Second brace beam concreting completed. Third stage column concreting completed. Third brace beam shuttering and steel work progressing..