- Home
- Deposite work -Kollam jilla panchayat- P...
Deposite work -Kollam jilla panchayat- Pipe line extension by 75mm pvc pipe and 65mmGI pipee to Valayicodu kunnuvilabhagom and providing house connections in Ezhukone panchayat
| Project |
Deposite work -Kollam jilla panchayat- Pipe line extension by 75mm pvc pipe and 65mmGI pipee to Valayicodu kunnuvilabhagom and providing house connections in Ezhukone panchayat |
| Project Code |
KLMDEPO03217931 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
Deposite work -Kollam jilla panchayat- Pipe line extension by 75mm pvc pipe and 65mmGI pipee to Valayicodu kunnuvilabhagom and providing house connections in Ezhukone panchayat |
| Status |
Completed |
| District |
Kollam |
| Executing Office |
Kottarakkara PH Dn |
| AS Amount (Rs) |
3394000
|
| AS Number |
U000000858811384 |
| TS Amount (Rs) |
1407000 |
| TS Number |
TS/2021-2022/2021/9123 |
| Total Bill Submitted (Rs) |
1 |
| Total Bill Paid (Rs) |
1 |
| Population Benefitted |
1200 |
| Capacity in MLD |
8.00 |
| Actual Project Completion Date |
15 Nov 2021 |
| Coverage |
Ezhukone |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Deposite work -Kollam jilla panchayat- Pipe line extension by 75mm pvc pipe and 65mmGI pipee to Valayicodu kunnuvilabhagom and providing house connections in Ezhukone panchayat |
Kundara PH Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 27 Dec 2021 |
Work completed and bill under preparation |
Kottarakkara PH Dn EE |
|
| 21 Dec 2021 |
work in progress |
Kottarakkara PH Dn EE |
|
| 17 Dec 2021 |
Work in progress |
Kottarakkara PH Dn EE |
|
| 12 Dec 2021 |
Work in progress |
Kottarakkara PH Dn EE |
|
| 07 Dec 2021 |
Work in progress |
Kottarakkara PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
30/08/2021 |
| Scheduled date of Completion of the Project |
05 Nov 2021 |
| Expected date of Completion |
30/11/2021 |
Processing Dates
| AS Date |
25 Mar 2021 |
| TS Date |
06 May 2021 |