Project | Jal Jeevan Mission(JJM)-RWSS- Chittar construction of 0.9LL capacity GLSR at Neelipilavu top-At Neelipilavu top- General civil work. |
---|---|
Project Code | PTAJJM092113968P1 |
Type | Package |
Main Project | Jal Jeevan Mission(JJM)-RWSS- Chittar construction of 0.9LL capacity GLSR at Neelipilavu top-At Neelipilavu top- General civil work. General civil work. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission(JJM)-RWSS- Chittar construction of 0.9LL capacity GLSR at Neelipilavu top-At Neelipilavu top- General civil work. |
Status | On-going |
District | Pathanamthitta |
Executing Office | Vadasserikara Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 623880000 |
TS Number | TS/12035/2022_5_1_1 |
Technical specification | Jal Jeevan Mission(JJM)-RWSS- Chittar construction of 0.9LL capacity GLSR at Neelipilavu top-At Neelipilavu top- General civil work. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 24/04/2023 |
---|---|
Scheduled date of Completion as per agreement | 24 Apr 2024 |
Expected date of Completion | 24/04/2024 |
TS Date | 09 Mar 2023 |
---|---|
Estimate Approval | 09 Mar 2023 |
NIT Approval | 28 Feb 2023 |
Tender Closing | 27 Mar 2023 |
Price bid opening | 28 Mar 2023 |
Workorder Date | 01 Apr 2023 |
---|---|
NA | 24 Apr 2023 |
Vadasserikara PH Sn - AE |
Date: 26/06/2024 |
Work in progress | 25% Completed
Plinth level completed, Time extension submitted by the Contractor on 01/04/2024.
Vadasserikara PH Sn - AE |
Date: 24/06/2024 |
Work in progress | 25% Completed
Plinth level completed, Time extension submitted by the Contractor on 01/04/2024 .