Jal Jeevan Mission(JJM)-RWSS- Chittar construction of 0.9LL capacity GLSR at Neelipilavu top-At Neelipilavu top- General civil work.

Project Jal Jeevan Mission(JJM)-RWSS- Chittar construction of 0.9LL capacity GLSR at Neelipilavu top-At Neelipilavu top- General civil work.
Project Code PTAJJM092113968P1
Type Package
Main Project Jal Jeevan Mission(JJM)-RWSS- Chittar construction of 0.9LL capacity GLSR at Neelipilavu top-At Neelipilavu top- General civil work. General civil work.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission(JJM)-RWSS- Chittar construction of 0.9LL capacity GLSR at Neelipilavu top-At Neelipilavu top- General civil work.
Status On-going
District Pathanamthitta
Executing Office Vadasserikara Sn
Agreement Number
Agreement Date
TS Amount (Rs) 623880000
TS Number TS/12035/2022_5_1_1
Technical specification Jal Jeevan Mission(JJM)-RWSS- Chittar construction of 0.9LL capacity GLSR at Neelipilavu top-At Neelipilavu top- General civil work.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/04/2023
Scheduled date of Completion as per agreement 24 Apr 2024
Expected date of Completion 24/04/2024

Processing Dates

TS Date 09 Mar 2023
Estimate Approval 09 Mar 2023
NIT Approval 28 Feb 2023
Tender Closing 27 Mar 2023
Price bid opening 28 Mar 2023

Approval Dates

Workorder Date 01 Apr 2023
NA 24 Apr 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vadasserikara PH Sn - AE
Date: 26/06/2024

Work in progress | 25% Completed

Plinth level completed, Time extension submitted by the Contractor on 01/04/2024.

Vadasserikara PH Sn - AE
Date: 24/06/2024

Work in progress | 25% Completed

Plinth level completed, Time extension submitted by the Contractor on 01/04/2024 .