Project | KIIFB -WRD 002-11- WSS TO MATTANNUR & IRITTY MUNICIPALITIES- PACKAGE I |
---|---|
Project Code | KNRKIIFB0117528P1 |
Type | Package |
Main Project | KIIFB -WRD 002-11 -WSS TO MATTANNUR AND IRITTY MUNICIPALITIES |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Intake well ( 12 m dia) cum Pump house Raw Water Pumping Main (750mm DI K9(3400 m) and 750 MS (300 m) Raw water pumpset (600 VT Pumpsets - 2 Nos) Transformer (1500 KVA 2 Nos, 100 KVA 1 No) including substation building |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 184500000 |
TS Number | KWA/CE/NR/D2-348/2017 |
Technical specification | Construction of Intake well cum Pump house, Raw Water Pumping Main, Raw Water Pump set, Transformer and Substation building. |
Contractor | Reena Engineers and Contractors Pvt.Ltd (Mob: 9447026559) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 10/07/2017 |
---|---|
Scheduled date of Completion as per agreement | 09 Jan 2019 |
Expected date of Completion | 31/05/2021 |
TS Date | 04 Mar 2017 |
---|---|
Estimate Approval | 04 Mar 2017 |
Tender Closing | 28 Mar 2017 |
Price bid opening | 01 Apr 2017 |
Workorder Date | 10 Jul 2017 |
---|---|
NA | 21 Oct 2017 |
Mattannur Project Sn 2 AE |
Date: 05/08/2021 |
Work has been completed | 100% Completed
Trial run completed.
Mattannur Project Sn 2 AE |
Date: 04/08/2021 |
Work in progress | 99% Completed