WSS to Seethathode & Perunadu Panchayats (Nilackal)-Phase II- Package III

Project WSS to Seethathode & Perunadu Panchayats (Nilackal)-Phase II- Package III
Project Code PTANABARD1219604P3
Type Package
Main Project NABARD-RIDF-XXIV-WSS to Seethathode & Perunadu Panchayats (Nilackal)-Phase II
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme 4215-01-102-98 (01)
Description Construction of intermediate tanks for Laha, Kisumam, CWPM and distribution systems for Laha, Thulappally, Kisumam, Attathodu etc.
Status On-going
District Pathanamthitta
Executing Office Adoor Project Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification Construction of intermediate tanks for Laha, Kisumam, CWPM and distribution systems for Laha, Thulappally, Kisumam, Attathodu etc.

Project Review

See All Review messages
Review Date Review Message Review Attended By
03 Mar 2022 Advance possession of land at Thulappally obtained EE, AE, Panchayath president

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
17 Feb 2022 Pending 18 Feb 2022 Approval/Permissions Related (from other departments excluding road cut permission and land related) Soil investigation to be conducted Completed Action Taken

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/05/2022
Scheduled date of Completion as per agreement 17 Apr 2023
Expected date of Completion 31/03/2024

Processing Dates

Estimate Approval 30 Mar 2022
NIT Approval 30 Mar 2022
Tender Closing 20 Apr 2022
Technichal Pre-Qualification 20 Apr 2022
Price bid opening 25 Apr 2022

Approval Dates

Workorder Date 30 Apr 2022
NA 10 May 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Adoor Project Dn - AE 5
Date: 01/02/2025

Work has started | 0% Completed

Reappropriation sanction obtained, estimate resubmitted.

Adoor Project Dn - AE 5
Date: 22/01/2025

Work has started | 0% Completed

Reappropriation sanction obtained, estimate resubmitted.