DEPOSIT-RWSS to Thrikovilvattom-Installation of Pumpset ,Accessories in existing Pump house & Tube Well at Thattarkonam -Kuthiramukku
Project Code
KLMDEPO082517756
Type
Main project
Funding Agency
DEPO
Category
Deposit Work
Type of scheme
Water Supply
Scheme
DEPO
Description
DEPOSIT-RWSS to Thrikovilvattom-Installation of Pumpset ,Accessories in existing Pump house & Tube Well at Thattarkonam -Kuthiramukku
Status
Completed
District
Kollam
Executing Office
Kottiyam PH Sn
AS Amount (Rs)
540000
AS Number
A3-151/2025
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date
20 Feb 2026
Coverage
Packages
No.
Project Name
Location
View
No Packages has been added for this project.
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
21 Feb 2026
Work completed.
Kottiyam PH Sn AE
16 Feb 2026
Pannel board fixed for electricity connection. KSEB estimate for the supply of electricity has been submitted to Sub Division.Roof work completed. Got an electric connection.Interconnection of pumping main to the existing line completed.New 5 HP pump erected,brick work, plastering,Painting works and Bleaching powder stacking room and Chlorination unit work has been completed.trial running has been done
Kottiyam PH Sn AE
13 Feb 2026
Pannel board fixed for electricity connection. KSEB estimate for the supply of electricity has been submitted to Sub Division.Roof work completed. Got an electric connection.Interconnection of pumping main to the existing line completed.New 5 HP pump erected,brick work, plastering,Painting works and Bleaching powder stacking room and Chlorination unit work has been completed.trial running has been done
Kottiyam PH Sn AE
10 Feb 2026
Pannel board fixed for electricity connection. KSEB estimate for the supply of electricity has been submitted to Sub Division.Roof work completed. Got an electric connection.Interconnection of pumping main to the existing line completed.New 5 HP pump erected,brick work, plastering,Painting works and Bleaching powder stacking room and Chlorination unit work has been completed.
Kottiyam PH Sn AE
04 Feb 2026
Pannel board fixed for electricity connection. KSEB estimate for the supply of electricity has been submitted to Sub Division.Roof work completed. Got an electric connection.Interconnection of pumping main to the existing line completed.New 5HP pump erected,brick work completed , plastering work completed .