Project | JJM - Padiyur Grama Panchayath - Providing FHTC to Rural house holds, Retrofitting & Augmentation of existing water supply schemes. |
---|---|
Project Code | TCRJJM08203903P1 |
Type | Package |
Main Project | JJM - Padiyur GramaPanchayath - RDWSS to Karalam, Kattoor, Padiyoor, Poomangalam - Providing FHTC to Rural house holds |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM - Padiyur Grama Panchayath - Providing FHTC to Rural house holds, Retrofitting & Augmentation of existing water supply schemes. |
Status | On-going |
District | Thrissur |
Executing Office | Irinjalakkuda PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 16400000 |
TS Number | TS/2020-2021/2020/14417 |
Technical specification | Providing FHTC to Rural house holds, Retrofitting & Augmentation of existing water supply schemes. |
Contractor | M/S Stev and Jols Project Solutions Private Limited (Mob: 8850167071) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
13 Oct 2021 | Pending | Pending | Natural Calamities Related | Due to high water table trenching works cannot be carried out in Padiyur GP | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/08/2020 |
---|---|
Scheduled date of Completion as per agreement | 05 May 2021 |
Expected date of Completion | 31/05/2023 |
TS Date | 22 Aug 2020 |
---|---|
Estimate Approval | 28 Feb 2020 |
NIT Approval | 28 Feb 2020 |
Tender Closing | 14 Oct 2020 |
Technichal Pre-Qualification | 14 Oct 2020 |
Price bid opening | 14 Oct 2020 |
Workorder Date | 06 Nov 2020 |
---|---|
NA | 16 Feb 2021 |
Irinjalakuda AE |
Date: 08/05/2023 |
Work has been completed | 100% Completed
1757 FHTC completed out of 1979nos. 222nos FHTC to be provided for the complete coverage as per IMIS data sheet. Since the amount of work exceeds above the PAC amount, the work stopped after the discussion with higher officials..
Irinjalakuda AE |
Date: 07/05/2023 |
Work in progress | 92% Completed
Providing FHTC is in progress..