Project | Providing balance Pipe line work (PWD Roads) in Muthuvallur Grama Panchayath |
---|---|
Project Code | MLPJJM08203222P4 |
Type | Package |
Main Project | JJM-2020-21 Providing FHTC inMuthuvallur Gramapanchayth in Malappuram District-On going Scheme |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Providing balance Pipe line work (PWD Roads) in Muthuvallur Grama Panchayath |
Status | Short Closed |
District | Malappuram |
Executing Office | Malappuram Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 9900000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/16602/2022_26_4_2 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | 29 Feb 2024 |
Expected date of Completion | 29/02/2024 |
TS Date | 01 Nov 2023 |
---|
NA | 19 Dec 2023 |
---|
Malapuram Proj Dn AE 4 |
Date: 28/06/2024 |
Work in progress | 10% Completed
No work.
Malapuram Proj Dn AE 4 |
Date: 27/06/2024 |
Work in progress | 10% Completed
No work.