Project | Jal Jeevan Mission (JJM)-JJM 2020 -21 TVPM District - Parassala Panchayath - Phase 2 Water supply line extension and providing water connection from the proposed pipe lines to house holds of Parassala Grama Panchayath - Panchayath Road Restoration work -JJM 2020 -21 TVPM District - Parassala Panchayath - Phase 2 Water supply line extension and providing water connection from the proposed pipe lines to house holds of Parassala Grama Panchayath - Panchayath Road Restoration work-Pipeline Work-Road restoration work |
---|---|
Project Code | TVMJJM022214953P2 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-JJM III -Jal Jeevan Mission - Parassala Grama Panchayath Phase III - Pipe line extension of existing distribution Network and providing FHTC to House holds in Parassala Grama Panchayath - OHSR Vandichira Parasuvikal Zone, Parassala Zone, Kodavilakam Zone -Pipeline Work |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-JJM 2020 -21 TVPM District - Parassala Panchayath - Phase 2 Water supply line extension and providing water connection from the proposed pipe lines to house holds of Parassala Grama Panchayath - Panchayath Road Restoration work -JJM 2020 -21 TVPM District - Parassala Panchayath - Phase 2 Water supply line extension and providing water connection from the proposed pipe lines to house holds of Parassala Grama Panchayath - Panchayath Road Restoration work-Pipeline Work-Road restoration work |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Parassala WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 24150000 |
TS Number | TS/13460/2023 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 10/08/2023 |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | 09/08/2024 |
TS Date | 25 Jul 2023 |
---|
Parassala WS Sn |
Date: 28/06/2024 |
Work in progress | 60% Completed
No work .
Parassala WS Sn |
Date: 26/06/2024 |
Work in progress | 60% Completed
No work .