Jal Jeevan Mission - Thrikkovilvattam Grama Panchayath - Restoration on kottiyam Kundara road

Project Jal Jeevan Mission - Thrikkovilvattam Grama Panchayath - Restoration on kottiyam Kundara road
Project Code KLMJJM08203112P2
Type Package
Main Project Jal Jeevan Mission - Providing Functional Household Tap Connections and laying distribution system at Thrikkovilvattom Panchayath in Kollam District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission - Thrikkovilvattam Grama Panchayath - Restoration on Kottiyam Kundara road
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 1153000
TS Number 2021-2022/2021/26854
Technical specification
Contractor Sohail shamsudeen (Mob: 9809509114)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/11/2022
Scheduled date of Completion as per agreement 12 Feb 2023
Expected date of Completion 12/02/2023

Processing Dates

TS Date 08 Nov 2021
Estimate Approval 08 Nov 2021
NIT Approval 18 Jul 2022
Tender Closing 22 Sep 2022
Price bid opening 24 Sep 2022

Approval Dates

Workorder Date 10 Oct 2022
NA 13 Oct 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 10/01/2023

Work has been completed | 100% Completed

Work completed.

Kollam Project Dn AE
Date: 09/01/2023

Work in progress | 99% Completed

Road Restoration Taring work progressing at Kottiyam Kundara road.