| Project | Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Kadangode Panchayath-Providing Distribution Network and FHTC to Kadangode Panchayath |
|---|---|
| Project Code | TCRJJM052213583P1 |
| Type | Package |
| Main Project | Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Kadangode Panchayath-Providing Distribution Network and FHTC to Kadangode Panchayath |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Kadangode Panchayath-Providing Distribution Network and FHTC to Kadangode Panchayath |
| Status | On-going |
| District | Thrissur |
| Executing Office | Nattika Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 658200000 |
| TS Number | WRD/KWA-CE(CR)EST-TS/2763/2022-26_1_1 |
| Technical specification | Providing Distribution Network and FHTC to Kadangode Panchayath |
| Contractor | HUNIFA MEETHAL (Mob: 9746924449) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 08/02/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 05 Jan 2024 |
| Expected date of Completion | 30/05/2025 |
| TS Date | 21 Oct 2022 |
|---|---|
| Estimate Approval | 21 Oct 2022 |
| Tender Closing | 19 Nov 2022 |
| Technichal Pre-Qualification | 21 Nov 2022 |
| Price bid opening | 23 Dec 2022 |
| Workorder Date | 05 Jan 2023 |
|---|---|
| NA | 23 Jan 2023 |
| Nattika Project Dn EE |
| Date: 15/07/2026 |
Work in progress | 61% Completed
Pipe Supplied -127328.5/180610m Pipe laid- 99790m/121384m HTC given = 2938/5724 Nos. Geo Tagging- 2938/2938 Nos. BT Restoration- 31000m, GSB/WMM Restoration- 55500m, Restoration by PCC 2500m. Pipe line laid-(75 mm PVCPIPE(6 kg/cm2)= 6558m, 63 mm PVCPIPE(6 kg/cm2) =12286m, 50 mm PVC PIPE (6 kg/cm2) = 845m, 40mm PVC PIPE(Not in drwng)=72m, 100mm GI Pipe = 109 m 80mm GI Pipe = 268 m 150mm GI pipe= 41 m 90 mm HDPE PIPE = 48550.m 110 mm HDPE PIPE=13666.m 160 mm HDPE PIPE = 9449.5m 200 mm DI = 1374.2m 400 mm DI = 647.6m 350 mm DI = 115.5 m 450 mm DI = 1924.7 m, 500 mm DI =42M, 90 mm PVC =4104.3m). .
| Nattika Project Dn EE |
| Date: 14/07/2026 |
Work in progress | 61% Completed
Pipe Supplied -127328.5/180610m Pipe laid- 99790m/121384m HTC given = 2938/5724 Nos. Geo Tagging- 2938/2938 Nos. BT Restoration- 31000m, GSB/WMM Restoration- 55500m, Restoration by PCC 2500m. Pipe line laid-(75 mm PVCPIPE(6 kg/cm2)= 6558m, 63 mm PVCPIPE(6 kg/cm2) =12286m, 50 mm PVC PIPE (6 kg/cm2) = 845m, 40mm PVC PIPE(Not in drwng)=72m, 100mm GI Pipe = 109 m 80mm GI Pipe = 268 m 150mm GI pipe= 41 m 90 mm HDPE PIPE = 48550.m 110 mm HDPE PIPE=13666.m 160 mm HDPE PIPE = 9449.5m 200 mm DI = 1374.2m 400 mm DI = 647.6m 350 mm DI = 115.5 m 450 mm DI = 1924.7 m, 500 mm DI =42M, 90 mm PVC =4104.3m). .