Jal Jeevan Mission (JJM)-Kannur District- Peralassery Pt-WSS to Anjarakandy and Adjoining Panchayaths-Balance work-Laying distribution and providing FHTC- Pipeline Work

Project Jal Jeevan Mission (JJM)-Kannur District- Peralassery Pt-WSS to Anjarakandy and Adjoining Panchayaths-Balance work-Laying distribution and providing FHTC- Pipeline Work
Project Code KNRJJM08202945P2
Type Package
Main Project JJM - Kannur District- Peralassery Panchayath - WSS to Anjarakandy and Adjoing Panchayath Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Kannur District- Peralassery Pt-WSS to Anjarakandy and Adjoining Panchayaths-Balance work-Laying distribution and providing FHTC- Pipeline Work
Status On-going
District Kannur
Executing Office Perlassery Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 12100000
TS Number 8058/2022-2023
Technical specification
Contractor MOHANAN V (Mob: 9447281704)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 09/12/2022
Scheduled date of Completion as per agreement 23 May 2023
Expected date of Completion 30/04/2023

Processing Dates

TS Date 09 Dec 2022
Estimate Approval 09 Dec 2022
NIT Approval 15 Dec 2022
Tender Closing 29 Dec 2022
Technichal Pre-Qualification 30 Dec 2022
Price bid opening 30 Dec 2022

Approval Dates

Workorder Date 18 Jan 2023
NA 24 Jan 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Perlassery Sn 2 AE
Date: 25/06/2024

Work in progress | 95% Completed

689Nos FHTCS provided. 1.93km laying and 653nos FHTCS bill submitted.

Perlassery Sn 2 AE
Date: 18/06/2024

Work in progress | 95% Completed

658Nos FHTCS provided. 1.93km laying and 653nos FHTCS bill submitted.