State Plan-2019-20 Rural Water supply schemes. Water supply scheme to Cheekode and adjoining villages Phase II-Urgent pipe laying and providing FHTCs along Puthupadam-Ayikkarappadi-Kakkancheri PWD road in Cherukavu panchayath-Pipe line work

Project State Plan-2019-20 Rural Water supply schemes. Water supply scheme to Cheekode and adjoining villages Phase II-Urgent pipe laying and providing FHTCs along Puthupadam-Ayikkarappadi-Kakkancheri PWD road in Cherukavu panchayath-Pipe line work
Project Code MLPGOK062415920
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan-2019-20 Rural Water supply schemes. Water supply scheme to Cheekode and adjoining villages Phase II-Urgent pipe laying and providing FHTCs along Puthupadam-Ayikkarappadi-Kakkancheri PWD road in Cherukavu Panchayath-Pipe line work
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
AS Amount (Rs) 400000000
AS Number GO(Rt)No.426/2020/WRD
TS Amount (Rs) 1960000
TS Number 28509/2023-2024
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 State Plan-2019-20 Rural Water supply schemes. Water supply scheme to Cheekode and adjoining villages Phase II-Urgent pipe laying and providing FHTCs along Puthupadam-Ayikkarappadi-Kakkancheri PWD road in Cherukavu panchayath-Pipe line work Project Division Malappuram

No status have been added to this project

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 16/04/2024
Scheduled date of Completion of the Project 16 Sep 2024
Expected date of Completion Date is not specified

Processing Dates

AS Date 26 Jun 2020
TS Date 27 Feb 2024

Other details

Project Officers View