JJM 2021-24-Aryanadu Uzhamalakkal panchayaths Phase-III

Project JJM 2021-24-Aryanadu Uzhamalakkal panchayaths Phase-III
Project Code TVMJJM022114627
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description 1. Construction of 9.00 dia well cum pump house near Eliyavoor bridge Uzhamalakkal Panchayath. 2.Distribution from Mangattupara sump to Uzhamalakkal Panchayaths 3.Distribution from pallivetta OHSR to Aryanadu Panchayaths(4400 FHTC) 4. .Distribution from Vettichankunnu OHSR to Aryanadu Panchayath. 5.Distribution from Mangattupara GLSR to Uzhamalakkal Panchayaths(2626 FHTC). 6.Construction of 11.50 MLD WTP at Mangattupara Uzhamalakkal Panchayath.
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
AS Amount (Rs) 1463921000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 7702
TS Number 2911/2023_26_1_1)
Total Bill Submitted (Rs) 122635423
Total Bill Paid (Rs) 35000000
Population Benefitted 47833
Capacity in MLD 11.50
Actual Project Completion Date Date is not specified
Coverage Aryanadu and Uzhamalakkal Panchayath

Packages

No. Project Name Location View
1 Construction of dia well cum pump house near eliyavoor bridge,package1 Trivandrum Project Dn
2 Distribution from Mangattupara GLSR to Uzhamalakkal Panchayaths,Package 5 Trivandrum Project Dn
3 Distribution from Mangattupara sump to Uzhamalakkal Panchayaths,Package 2 Trivandrum Project Dn
4 Distribution from pallivetta to Aryanad Panchayaths,Package 3 Trivandrum Project Dn
5 Distribution from Vettichankunnu OHSR,Package 4 Trivandrum Project Dn
6 JJM 2021-2024 Mangattupara GP -11.5 MLD plant package 6 Trivandrum Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Feb 2024 Package-1-Construction of 9.00m dia well cum pump house at Eleyavoor-1%, Package-2-Distribution from Mangattupara Sump to Uzhamalakkal Panchayath-pipe line work-47%,Package-3 Distribution from Pallivetta OHSR to Aryanadu Panchayath Panchayath-Pipe line work-57% ,Package-4-Distribution from Vettichankunnu OHSR to Aryanadu Panchayath-Pipe line work-46%,Package-5-Distribution from Mangattupara GLSR to Uzhamalakkal Panchayath- Pipe line work-49%,Construction of 11.50 MLD WTP at Mangattupara ,Uzhamalakkal Pancayath-2% Thiruvananthapuram Project - AE 11
13 Feb 2024 Package-1-Construction of 9.00m dia well cum pump house at Eleyavoor,-, Package-2-Distribution from Mangattupara Sump to Uzhamalakkal Panchayath,Package-3 Distribution from Pallivetta OHSR to Aranadu Panchayath Panchayath ,Package-4-Distribution from Vettichankunnu OHSR to Aryanadu Panchayath-Pipe line work,Package-5-Distribution from Mangattupara GLSR to Uzhamalakkal Panchayath,Construction of 11.50 MLD WTP at Mangattupara ,Uzhamalakkal Pancayath. Thiruvananthapuram Project - AE 11
13 Feb 2024 ongoing Thiruvananthapuram Project - AE 11

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 17/05/2023
Scheduled date of Completion of the Project 12 Mar 2025
Expected date of Completion 12/03/2025

Processing Dates

AS Date 23 Feb 2022
TS Date 28 Mar 2023

Other details