- Home
- JJM 2021-24-Aryanadu Uzhamalakkal pancha...
JJM 2021-24-Aryanadu Uzhamalakkal panchayaths Phase-III
Project |
JJM 2021-24-Aryanadu Uzhamalakkal panchayaths Phase-III |
Project Code |
TVMJJM022114627 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
1. Construction of 9.00 dia well cum pump house near Eliyavoor bridge Uzhamalakkal Panchayath.
2.Distribution from Mangattupara sump to Uzhamalakkal
Panchayaths
3.Distribution from pallivetta OHSR to Aryanadu Panchayaths(4400 FHTC)
4. .Distribution from Vettichankunnu OHSR to Aryanadu Panchayath.
5.Distribution from Mangattupara GLSR to Uzhamalakkal
Panchayaths(2626 FHTC).
6.Construction of 11.50 MLD WTP at Mangattupara Uzhamalakkal Panchayath. |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
1463921000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
7702 |
TS Number |
2911/2023_26_1_1) |
Total Bill Submitted (Rs) |
122635423 |
Total Bill Paid (Rs) |
35000000 |
Population Benefitted |
47833 |
Capacity in MLD |
11.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Aryanadu and Uzhamalakkal Panchayath |
Packages
No. |
Project Name |
Location |
View |
1 |
Construction of dia well cum pump house near eliyavoor bridge,package1 |
Trivandrum Project Dn |
|
2 |
Distribution from Mangattupara GLSR to Uzhamalakkal Panchayaths,Package 5 |
Trivandrum Project Dn |
|
3 |
Distribution from Mangattupara sump to Uzhamalakkal Panchayaths,Package 2 |
Trivandrum Project Dn |
|
4 |
Distribution from pallivetta to Aryanad Panchayaths,Package 3 |
Trivandrum Project Dn |
|
5 |
Distribution from Vettichankunnu OHSR,Package 4 |
Trivandrum Project Dn |
|
6 |
JJM 2021-2024 Mangattupara GP -11.5 MLD plant package 6 |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Feb 2024 |
Package-1-Construction of 9.00m dia well cum pump house at Eleyavoor-1%, Package-2-Distribution from Mangattupara Sump to Uzhamalakkal Panchayath-pipe line work-47%,Package-3 Distribution from Pallivetta OHSR to Aryanadu Panchayath Panchayath-Pipe line work-57% ,Package-4-Distribution from Vettichankunnu OHSR to Aryanadu Panchayath-Pipe line work-46%,Package-5-Distribution from Mangattupara GLSR to Uzhamalakkal Panchayath- Pipe line work-49%,Construction of 11.50 MLD WTP at Mangattupara ,Uzhamalakkal Pancayath-2% |
Thiruvananthapuram Project - AE 11 |
|
13 Feb 2024 |
Package-1-Construction of 9.00m dia well cum pump house at Eleyavoor,-, Package-2-Distribution from Mangattupara Sump to Uzhamalakkal Panchayath,Package-3 Distribution from Pallivetta OHSR to Aranadu Panchayath Panchayath ,Package-4-Distribution from Vettichankunnu OHSR to Aryanadu Panchayath-Pipe line work,Package-5-Distribution from Mangattupara GLSR to Uzhamalakkal Panchayath,Construction of 11.50 MLD WTP at Mangattupara ,Uzhamalakkal Pancayath. |
Thiruvananthapuram Project - AE 11 |
|
13 Feb 2024 |
ongoing |
Thiruvananthapuram Project - AE 11 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
17/05/2023 |
Scheduled date of Completion of the Project |
12 Mar 2025 |
Expected date of Completion |
12/03/2025 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
28 Mar 2023 |