Jal Jeevan Mission-Providing Functional Household Tap Connections and Laying of Balance distribution network at Mylom Panchayath

Project Jal Jeevan Mission-Providing Functional Household Tap Connections and Laying of Balance distribution network at Mylom Panchayath
Project Code KLMJJM08203115P2
Type Package
Main Project Jal Jeevan Mission-Providing Functional Household Tap Connections and Laying of Balance distribution network at Mylom Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission-Providing Functional Household Tap Connections and Laying of Balance distribution network at Mylom Panchayath
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 159120000
TS Number TS/2020-21/2020/14116
Technical specification Supply and laying 180 kms of distribution network and providing 9102 FHTCs.
Contractor M/s. Tomco Engineering (P) Ltd (Mob: 9447082222)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/02/2021
Scheduled date of Completion as per agreement 09 Sep 2022
Expected date of Completion 30/12/2022

Processing Dates

TS Date 02 Sep 2020
Estimate Approval 02 Sep 2020
NIT Approval 14 Sep 2020
Tender Closing 10 Nov 2020
Technichal Pre-Qualification 18 Nov 2020
Price bid opening 30 Nov 2020

Approval Dates

Workorder Date 23 Dec 2020
NA 10 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn AE
Date: 29/06/2024

Work in progress | 87% Completed

7426 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 .

Kollam Project Dn AE
Date: 28/06/2024

Work in progress | 87% Completed

7426 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 .