Project | Jal Jeevan Mission-Providing Functional Household Tap Connections and Laying of Balance distribution network at Mylom Panchayath |
---|---|
Project Code | KLMJJM08203115P2 |
Type | Package |
Main Project | Jal Jeevan Mission-Providing Functional Household Tap Connections and Laying of Balance distribution network at Mylom Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission-Providing Functional Household Tap Connections and Laying of Balance distribution network at Mylom Panchayath |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 159120000 |
TS Number | TS/2020-21/2020/14116 |
Technical specification | Supply and laying 180 kms of distribution network and providing 9102 FHTCs. |
Contractor | M/s. Tomco Engineering (P) Ltd (Mob: 9447082222) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 10/02/2021 |
---|---|
Scheduled date of Completion as per agreement | 09 Sep 2022 |
Expected date of Completion | 30/12/2022 |
TS Date | 02 Sep 2020 |
---|---|
Estimate Approval | 02 Sep 2020 |
NIT Approval | 14 Sep 2020 |
Tender Closing | 10 Nov 2020 |
Technichal Pre-Qualification | 18 Nov 2020 |
Price bid opening | 30 Nov 2020 |
Workorder Date | 23 Dec 2020 |
---|---|
NA | 10 Feb 2021 |
Kollam Project Dn AE |
Date: 29/06/2024 |
Work in progress | 87% Completed
7426 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 .
Kollam Project Dn AE |
Date: 28/06/2024 |
Work in progress | 87% Completed
7426 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 .