JJM-2022-2023 WSS to Pananchery, Puthur and Madakkathara Panchayaths-Providing distribution network and FHTC to Puthur Panchayath
Project |
JJM-2022-2023 WSS to Pananchery, Puthur and Madakkathara Panchayaths-Providing distribution network and FHTC to Puthur Panchayath |
Project Code |
TCRJJM052113960 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-2022-23 WSS to Pananchery, Puthur and Madakkathara Panchayaths-Providing distribution network and FHTC to Puthur panchayath |
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
1125213000
|
AS Number |
G.O.(Rt)No.401/2022/WRD |
TS Amount (Rs) |
867100000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/13087/2022_26_1_1 |
Total Bill Submitted (Rs) |
927337 |
Total Bill Paid (Rs) |
927337 |
Population Benefitted |
49234 |
Capacity in MLD |
14.50 |
Actual Project Completion Date |
15 Sep 2024 |
Coverage |
Puthur Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-2022-2023 WSS to Pananchery, Puthur and Madakkathara Panchayaths-Providing distribution network and FHTC to Puthur Panchayath |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
04 May 2024 |
supply today -0 m, cumulative 99369/266428 m Laying: Today: Total=660 m Cumulative-79716.4/266428m. HTC given today = 15nos. Uptodated HTC:888 nos. out of 11233. Geotagging Today: 0nos, Cumulative: 421 nos out of 11233. Road Restoration Today:-0 m Cumulative : 894.4m /266428 m |
Nattika Project Dn AE 4 |
|
03 May 2024 |
supply today -0 m, cumulative 99369/266428 m Laying: Today: Total=989 m Cumulative-79056.4/266428m. HTC given today = 12nos. Uptodated HTC:873 nos. out of 11233. Geotagging Today: 0nos, Cumulative: 421 nos out of 11233. Road Restoration Today:-0 m Cumulative : 894.4m /266428 m |
Nattika Project Dn AE 4 |
|
02 May 2024 |
supply today -0 m, cumulative 99369/266428 m Laying: Today: Total=693 m Cumulative-78067.4/266428m. HTC given today = 15nos. Uptodated HTC:861 nos. out of 11233. Geotagging Today: 0nos, Cumulative: 421 nos out of 11233. Road Restoration Today:-0 m Cumulative : 894.4m /266428 m |
Nattika Project Dn AE 4 |
|
01 May 2024 |
supply today -0 m, cumulative 99369/266428 m Laying: Today: Total=590 m Cumulative-77374.4/266428m. HTC given today = 11nos. Uptodated HTC:846 nos. out of 11233. Geotagging Today: 0nos, Cumulative: 421 nos out of 11233. Road Restoration Today:-0 m Cumulative : 894.4m /266428 m |
Nattika Project Dn AE 4 |
|
30 Apr 2024 |
supply today -0 m, cumulative 99369/266428 m Laying: Today: Total=520 m Cumulative-76784.4/266428m. HTC given today = 12nos. Uptodated HTC:835 nos. out of 11233. Geotagging Today: 0nos, Cumulative: 421 nos out of 11233. Road Restoration Today:-0 m Cumulative : 894.4m /266428 m |
Nattika Project Dn AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/03/2023 |
Scheduled date of Completion of the Project |
15 Sep 2024 |
Expected date of Completion |
15/09/2024 |
Processing Dates
AS Date |
13 May 2021 |
TS Date |
20 Dec 2022 |