KIIFB-2017-2018- CWSS to Perumatty , Pattanchery ,Nallepilly,Elappully Panchayaths in palakkad district--Phase II-Package-II

Project KIIFB-2017-2018- CWSS to Perumatty , Pattanchery ,Nallepilly,Elappully Panchayaths in palakkad district--Phase II-Package-II
Project Code PKDKIIFB1118624P2
Type Package
Main Project KIIFB-2017-2018- CWSS to Perumatty , Pattanchery ,Nallepilly,Elappully Panchayaths in palakkad district--Phase II
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB 2017-18 – CWSS to Perumatty, Pattenchery, Nalleppully, Elappully Panchayaths in Palakkad district – Phase II – Package II – Supplying and laying 350 mm DI K9 pipe for clear water Gravity main from kanakkanpara OHSR to Elappully propposed OHSR including Road restoration:
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 116821892
TS Number TS/2018-19/2018/15343 dated 21-02-2019
Technical specification Supplying and laying 350 mm DI K9 pipe for clear water Gravity main from kanakkanpara OHSR to Elappully propposed OHSR including Road restoration:
Contractor K.M Mohammed Rasheed (Mob: 9846200115)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/01/2020
Scheduled date of Completion as per agreement 21 Dec 2020
Expected date of Completion 31/05/2021

Processing Dates

TS Date 21 Feb 2019
Estimate Approval 21 Feb 2019
NIT Approval 13 Aug 2019
Tender Closing 19 Sep 2019
Technichal Pre-Qualification 19 Sep 2019
Price bid opening 19 Sep 2019

Approval Dates

NA 05 Feb 2020
Workorder Date 22 Jan 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - EE
Date: 23/08/2022

Work has been completed | 100% Completed

Final Bill to be uploaded.

Chittur Project Dn - AE 1
Date: 30/05/2022

Work has been completed | 100% Completed

BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation.