KIIFB-2017-2018- CWSS to Perumatty , Pattanchery ,Nallepilly,Elappully Panchayaths in palakkad district--Phase II-Package-II
Project |
KIIFB-2017-2018- CWSS to Perumatty , Pattanchery ,Nallepilly,Elappully Panchayaths in palakkad district--Phase II-Package-II |
Project Code |
PKDKIIFB1118624P2 |
Type |
Package |
Main Project |
KIIFB-2017-2018- CWSS to Perumatty , Pattanchery ,Nallepilly,Elappully Panchayaths in palakkad district--Phase II
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB 2017-18 – CWSS to Perumatty, Pattenchery, Nalleppully, Elappully Panchayaths in Palakkad district – Phase II – Package II – Supplying and laying 350 mm DI K9 pipe for clear water Gravity main from kanakkanpara OHSR to Elappully propposed OHSR including Road restoration: |
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
116821892 |
TS Number |
TS/2018-19/2018/15343 dated 21-02-2019 |
Technical specification |
Supplying and laying 350 mm DI K9 pipe for clear water Gravity main from kanakkanpara OHSR to Elappully propposed OHSR including Road restoration: |
Contractor |
K.M Mohammed Rasheed (Mob: 9846200115) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
22/01/2020 |
Scheduled date of Completion as per agreement |
21 Dec 2020 |
Expected date of Completion |
31/05/2021 |
Processing Dates
TS Date |
21 Feb 2019 |
Estimate Approval |
21 Feb 2019 |
NIT Approval |
13 Aug 2019 |
Tender Closing |
19 Sep 2019 |
Technichal Pre-Qualification |
19 Sep 2019 |
Price bid opening |
19 Sep 2019 |
Approval Dates
NA |
05 Feb 2020 |
Workorder Date |
22 Jan 2020 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Chittur Project Dn - EE |
Date: 23/08/2022 |
Work has been completed | 100% Completed
Final Bill to be uploaded.
Chittur Project Dn - AE 1 |
Date: 30/05/2022 |
Work has been completed | 100% Completed
BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation.