Project | Jal Jeevan Mission - Kannur District - Ezhome Grama Panchayath - WSS to Pattuvam and adj. Villages - Phase II |
---|---|
Project Code | KNRJJM08202991P1 |
Type | Package |
Main Project | Jal Jeevan Mission - Kannur District - Ezhome Grama Panchayath - WSS to Pattuvam and adj. Villages - Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission - Kannur District - Ezhome Grama Panchayath - WSS to Pattuvam and adj. Villages - Phase II |
Status | On-going |
District | Kannur |
Executing Office | Pilathra WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 57900000 |
TS Number | 16775/2020 -21 |
Technical specification | Laying 90mm,75mm,63mm,and 50mm 8kg/cm2 rating pipe as per KWA standards. Providing 2404 FHTCs by using standard materials like 2omm PVC 12.50kg/cm2 pipe double jet water meter brass ferrule full way GM wheel valve etc. |
Contractor | Paulson Chacko (Mob: 9447135650) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
01 Oct 2021 | Pending | Pending | Contract Related Risks | Contractor is not supplied pipes as per schedule. Now service connection pipe is exhausted. No meters, valves. No labours in the site due to payment issues. | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 10/11/2020 |
---|---|
Scheduled date of Completion as per agreement | 02 Mar 2021 |
Expected date of Completion | 31/05/2022 |
TS Date | 26 Aug 2020 |
---|---|
Estimate Approval | 20 Aug 2020 |
NIT Approval | 20 Aug 2020 |
Tender Closing | 28 Sep 2020 |
Price bid opening | 01 Sep 2021 |
Workorder Date | 03 Oct 2020 |
---|---|
NA | 27 Oct 2020 |
Pilathara WS Sn - AE |
Date: 24/06/2024 |
Work has been completed | 100% Completed
Work has been completed.Declared Har Ghar Jal..
Pilathara WS Sn - AE |
Date: 10/06/2024 |
Work has been completed | 100% Completed
Work has been completed.Declared Har Ghar Jal..