Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath -4th SLSSC-Part II- Extension of Distribution Line-General Civil Work.

Project Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath -4th SLSSC-Part II- Extension of Distribution Line-General Civil Work.
Project Code TCRJJM022214760P2
Type Package
Main Project Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath-- 4th SLSSC
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath -4th SLSSC-Part II- Extension of Distribution Line-General Civil Work.
Status On-going
District Thrissur
Executing Office Guruvayur PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 9900000
TS Number WRD/KWA-CE(CR)/EST_TS/17645/2023_5_1_1 Dated: 01-08-2023
Technical specification Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath -4th SLSSC-Part II- Extension of Distribution Line-General Civil Work.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/08/2023
Scheduled date of Completion as per agreement 24 Dec 2023
Expected date of Completion 31/07/2024

Processing Dates

TS Date 01 Aug 2023
Estimate Approval 01 Aug 2023
NIT Approval 11 Aug 2023
Tender Closing 18 Aug 2023
Technichal Pre-Qualification 18 Aug 2023
Price bid opening 19 Aug 2023

Approval Dates

Workorder Date 25 Aug 2023
NA 04 Sep 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Guruvayur PH Sn AE
Date: 29/06/2024

Work in progress | 75% Completed

5300m 160mm PVC pipe laid out of 6600m . Road restoration work to be arranged. second and part bill under scrutiny in division. .

Thrissur PH Dn EE
Date: 28/06/2024

Work in progress | 75% Completed

5300m 160mm PVC pipe laid out of 6600m . Road restoration work to be arranged. second and part bill under scrutiny in division..