| Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Beypore Zone |
|---|---|
| Project Code | CLTGOI0118511P1 |
| Type | Package |
| Main Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Distribution Lines in 10 Zone in Kozhikode corporation |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Beypore Zone |
| Status | Completed |
| District | Kozhikkode |
| Executing Office | Kozhikode Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 106800000 |
| TS Number | TS/1319/2018-2019 |
| Technical specification | scope of work- Supplying and Laying 180 mm PVC Pipe-45m 160 mm PVC Pipe-296m 140 mm PVC Pipe-147m 110 mm PVC Pipe-333m 90 mm PVC Pipe-589m 75 mm PVC Pipe-73248m 65 mm GI Pipe-900m |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 08/11/2018 |
|---|---|
| Scheduled date of Completion as per agreement | 02 Oct 2020 |
| Expected date of Completion | 28/02/2020 |
| TS Date | 19 Jul 2018 |
|---|---|
| Estimate Approval | 19 Jul 2018 |
| NIT Approval | 08 Nov 2018 |
| Tender Closing | 13 Aug 2018 |
| Price bid opening | 17 Aug 2018 |
| Workorder Date | 10 Oct 2018 |
|---|---|
| NA | 08 Nov 2018 |
| Kozhikode Project Dn AE5 |
| Date: 30/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.88373299/- final Bill paid to contractor on 16-10-2020 including Road restoration charges . .
| Kozhikode Project Dn AE5 |
| Date: 22/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.45514720/- final Bill paid to contractor on 16-10-2020 including Road restoration charges ..