- Home
- Jal Jeevan Mission (JJM)-JJM- WSS to Che...
Jal Jeevan Mission (JJM)-JJM- WSS to Chelakkara,Mullurkara and Panjal Panchayaths- Production components.-Construction of 15 MLD WTP at Mechrikunnu-General Civil Work
Project |
Jal Jeevan Mission (JJM)-JJM- WSS to Chelakkara,Mullurkara and Panjal Panchayaths- Production components.-Construction of 15 MLD WTP at Mechrikunnu-General Civil Work |
Project Code |
TCRJJM052215594 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Construction of 15 MLD WTP at Mechrikunnu |
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
2462533000
|
AS Number |
G.O.(Rt) No. 401/2022/WRD |
TS Amount (Rs) |
152600000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/1806/2022_5_2_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
15.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-JJM- WSS to Chelakkara,Mullurkara and Panjal Panchayaths- Production components.-Construction of 15 MLD WTP at Mechrikunnu-General Civil Work |
Nattika Project Dn |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
26/09/2023 |
Scheduled date of Completion of the Project |
25 Sep 2025 |
Expected date of Completion |
Date is not specified |
Processing Dates
AS Date |
13 May 2022 |
TS Date |
03 Aug 2023 |