Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission(JJM)-JJM-FULL COVERAGE IN KALLOORKKAD PANCHAYATH-PHASE II-PROVIDINGFTHC TO THE RURAL HOUSEHOLDS OF KALLORKKAD PANCHAYATH-General Civil Work

Project Jal Jeevan Mission(JJM)-JJM-FULL COVERAGE IN KALLOORKKAD PANCHAYATH-PHASE II-PROVIDINGFTHC TO THE RURAL HOUSEHOLDS OF KALLORKKAD PANCHAYATH-General Civil Work
Project Code EKMJJM022213247
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission(JJM)-JJM-FULL COVERAGE IN KALLOORKKAD PANCHAYATH-PHASE II-PROVIDINGFTHC TO THE RURAL HOUSEHOLDS OF KALLORKKAD PANCHAYATH-General Civil Work
Status On-going
District Ernakulam
Executing Office Muvattupuzha PH Dn
AS Amount (Rs) 413820000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 263720000
TS Number WRD/KWA-CE(CR)/EST_TS/2490/2022_5_1_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 2000
Capacity in MLD 5.00
Actual Project Completion Date 31 May 2024
Coverage KALLORKKAD PANCHAYATH

Packages

No. Project Name Location View
1 Jal Jeevan Mission(JJM)-JJM-FULL COVERAGE IN KALLOORKKAD PANCHAYATH-PHASE II-PROVIDINGFTHC TO THE RURAL HOUSEHOLDS OF KALLORKKAD PANCHAYATH-General Civil Work Muvattupuzha PH Circle

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 Work in progress Vazhakkulam PH Sn - AE
25 Jun 2024 Work in progress Vazhakkulam PH Sn - AE
24 Jun 2024 Work in progress Vazhakkulam PH Sn - AE
22 Jun 2024 Work in progress Vazhakkulam PH Sn - AE
21 Jun 2024 Work in progress Vazhakkulam PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/12/2022
Scheduled date of Completion of the Project 31 Aug 2023
Expected date of Completion 31/08/2023

Processing Dates

AS Date 23 Feb 2022
TS Date 17 Sep 2022

Other details

Project Officers View