DEPOSIT-Kannur Water Supply Scheme--RBDCK-Relaying of Gravity main and other distribution lines at Melechovva Junction related with construction of Flyover-Pipeline Work

Project DEPOSIT-Kannur Water Supply Scheme--RBDCK-Relaying of Gravity main and other distribution lines at Melechovva Junction related with construction of Flyover-Pipeline Work
Project Code KNRDEPO072518134P1
Type Package
Main Project DEPOSIT-Kannur Water Supply Scheme--RBDCK-Relaying of Gravity main and other distribution lines at Melechovva Junction related with construction of Flyover-Pipeline Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Kannur Water Supply Scheme--RBDCK-Relaying of Gravity main and other distribution lines at Melechovva Junction related with construction of Flyover-Pipeline Work
Status On-going
District Kannur
Executing Office Kannur WS Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 19770000
TS Number 14188/2025-2026
Technical specification
Contractor Shoney P Joseph (Mob: 9745608387)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 22 Sep 2025
NIT Approval 29 Sep 2025

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kannur WS Sn AE 2
Date: 25/09/2026

Work in progress | 6% Completed

Work started.Pipe supplied.160mm & 110 mm dia PVC Pipe-570 meter pipe laid.

Kannur WS Sn AE 2
Date: 14/08/2026

Work in progress | 6% Completed

Work started.Pipe supplied.160mm dia PVC Pipe-570 meter pipe laid..