AMRUT 2.0 - Providing FHTCs to Kondotty municipality (WSS to cheekode and adjoining villages)
Project |
AMRUT 2.0 - Providing FHTCs to Kondotty municipality (WSS to cheekode and adjoining villages) |
Project Code |
MLPAMRUT 2112214469 |
Type |
Main project |
Funding Agency |
AMRUT 2 |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
|
Description |
FHTCs |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram PH Dn |
AS Amount (Rs) |
176960000
|
AS Number |
G.O.(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
165000000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/9302/2022_26_1_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
Kondotty municipality |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2.0 - Providing FHTCs to Kondotty municipality (WSS to cheekode and adjoining villages) |
Kondotti PH Sn |
|
2 |
AMRUT 2.0-WSS for Kondotty Municipality |
Kondotti PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Jun 2024 |
FHTC work in progress, 1020 Nos. connections are completed |
Kondotty AE |
|
01 Jun 2024 |
FHTC work in progress, 1020 Nos. connections are completed |
Kondotty AE |
|
14 May 2024 |
FHTC work in progress, 900 Nos. connections are completed |
Kondotty AE |
|
09 May 2024 |
FHTC work in progress, 900 Nos. connections are completed |
Kondotty AE |
|
23 Apr 2024 |
FHTC work in progress, 900 Nos. connections are completed |
Kondotty AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/05/2023 |
Scheduled date of Completion of the Project |
01 May 2024 |
Expected date of Completion |
01/05/2024 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
27 Feb 2023 |