Project | JJM-2021-2022-Kizhakambalam Panchayath in Ernakulam District Phase III-Part -1 |
---|---|
Project Code | EKMJJM08203030P8 |
Type | Package |
Main Project | JJM - Providing FHTC to Rural house holds in Kizhakkambalam Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-2021-2022-Kizhakambalam Panchayath in Ernakulam District Phase III-Part -1 - Extension of pipe line in wrad1to 6 and providing Functional House Hold Tap Connections (FHTC) -Balance works |
Status | On-going |
District | Ernakulam |
Executing Office | Pattimattom PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 9966000 |
TS Number | 3484/2022-2023 dated 19.10.2022 |
Technical specification | |
Contractor | Abdul Salim K A (Mob: 8281888899) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 11/11/2022 |
---|---|
Scheduled date of Completion as per agreement | 10 Feb 2023 |
Expected date of Completion | 10/02/2023 |
TS Date | 19 Oct 2022 |
---|---|
Estimate Approval | 19 Oct 2022 |
NIT Approval | 19 Oct 2022 |
Tender Closing | 03 Nov 2022 |
Price bid opening | 05 Nov 2022 |
Workorder Date | 11 Nov 2022 |
---|---|
NA | 22 Nov 2022 |
Perumbavoor AEE |
Date: 27/06/2024 |
Work in progress | 46% Completed
3 rd part bill - 63mm pvc supply -3072mtr, 75mm pvc-400m,113 FHTC GIVEN .
Pattimattom - Kunnathunadu AE |
Date: 14/06/2024 |
Work in progress | 46% Completed
3 rd part bill - 63mm pvc supply -3072mtr, 75mm pvc-400m,113 FHTC GIVEN.