Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths-Package II |
---|---|
Project Code | PTAKIIFB0117560P2 |
Type | Package |
Main Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | This package includes Construction of 15LL -OHSR at Thirumoolapuram & Construction of 2 LL - Sump at Thirumoolapuram,Construction of 22 LL -OHSR at Thiruvalla & Construction of Office complex Thiruvalla,Laying transmission to Thirumoolapuram, Sump & pumping to OHSR,Clear water PM from Thiruvalla sump to OHSR,Distribution from Thirumoolapuram OH Tank,Distribution to Kuttupuzha area in Thiruvalla municipality,Construction of new roads and improvements of existing roads,Installation of solar panel for power production. |
Status | On-going |
District | Pathanamthitta |
Executing Office | Adoor Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 186600000 |
TS Number | KWA/CE(SR)/PHTVL/2788/2016 Dtd. 23/01/2017 |
Technical specification | This package includes Construction of 15LL -OHSR at Thirumoolapuram & Construction of 2 LL - Sump at Thirumoolapuram,Construction of 22 LL -OHSR at Thiruvalla & Construction of Office complex Thiruvalla,Laying transmission to Thirumoolapuram, Sump & pumping to OHSR,Clear water PM from Thiruvalla sump to OHSR,Distribution from Thirumoolapuram OH Tank,Distribution to Kuttupuzha area in Thiruvalla municipality,Construction of new roads and improvements of existing roads,Installation of solar panel for power production. |
Contractor | Abu Mathew (Mob: 9447037780) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
02 Sep 2019 | Pending | 20 Jul 2021 | Approval/Permissions Related (from other departments excluding road cut permission and land related) | RUB CROSSING PERMISSION PENDING | No comments added. | Action Taken |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 26/08/2017 |
---|---|
Scheduled date of Completion as per agreement | 25 Feb 2019 |
Expected date of Completion | 31/10/2021 |
TS Date | 23 Jan 2017 |
---|---|
Estimate Approval | 23 Jan 2017 |
NIT Approval | 23 Jan 2017 |
Tender Closing | 27 Mar 2017 |
Technichal Pre-Qualification | 30 Mar 2017 |
Price bid opening | 30 Mar 2017 |
NA | 26 Aug 2017 |
---|---|
Workorder Date | 13 Jun 2017 |
Adoor Project Dn AE3 |
Date: 27/10/2021 |
Work has been completed | 100% Completed
100 % work completed.
Adoor Project Dn AE3 |
Date: 04/10/2021 |
Work has been completed | 100% Completed
100 % WORK COMPLETED EXCEPT AGREEMENT WITH KSEB & ROB CROSSING.