Project | KIIFB 2017-18-CWSS to Karimba,Kongad and Mundur(part) panchayaths in Palakkad district-Laying 200mm DI-K9 pipe from Thuppanad Jn to 2LL OHSR at Kalladikode TB Jn &Siruvani canal jn to 2LL OHSR at Edakurussi along NH 966(Risk&Cost work) |
---|---|
Project Code | PKDKIIFB1118667P3 |
Type | Package |
Main Project | KIIFB 2017-18-Comprehensive drinking water scheme to Karimba and Kongad panchayaths in Mannarkkad and palakkad taluk in Palakkad Dt.-Phase I-Construction of pumphouse and control room, supplying and laying of raw water pumping main of 450mm dia DI K9 pipe for a length of 920m, construction, trial running and maintenance of 12 MLD WTP, construction of drainage pond at WTP premise, supplying and erection of RW and CW pumpsets and transformers. |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | KIIFB 2017-18-CWSS to Karimba,Kongad and Mundur(part) panchayaths in Palakkad district-Laying 200mm DI-K9 pipe from Thuppanad Jn to 2LL OHSR at Kalladikode TB Jn &Siruvani canal jn to 2LL OHSR at Edakurussi along NH 966(Risk&Cost work) |
Status | On-going |
District | Palakkad |
Executing Office | Palakkad Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 5263874 |
TS Number | TS/2021-2022/2021/41296 |
Technical specification | Laying 200mm DI-K9 Pipe |
Contractor | Noufal PK (Mob: 9207133135) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
09 Feb 2022 | Pending | Pending | Road Cut Related Risk | Laying the CWGM through NH-966 where the road is under refurbishment by PWD(NH).therefore coordination with the PWD dept is essential to commence the work. | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/01/2022 |
---|---|
Scheduled date of Completion as per agreement | 20 Feb 2022 |
Expected date of Completion | 30/11/2022 |
TS Date | 10 Dec 2021 |
---|---|
Estimate Approval | 10 Dec 2021 |
NIT Approval | 10 Jan 2022 |
Tender Closing | 14 Jan 2022 |
Technichal Pre-Qualification | 15 Jan 2022 |
Price bid opening | 15 Jan 2022 |
Workorder Date | 17 Jan 2022 |
---|---|
NA | 21 Jan 2022 |
Palakkad Project Dn EE |
Date: 13/03/2023 |
Work has been completed | 100% Completed
Pipelaying completed under condractors scope. .
Palakkad Proj AE 3 |
Date: 10/03/2023 |
Work in progress | 91% Completed
Pipelaying completed 91% only. Chamber works & interlinking completed. Balance laying kept on hold due to NH-966 widening works at Edakurissi area. ULCCS's Road formation work& Bridge construction creating hindrance to KWA works. Though road cutting permission obtained, pipelaying kept on hold till the completion of earth work by PWD..