Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB 2017-18-CWSS to Karimba,Kongad and Mundur(part) panchayaths in Palakkad district-Laying 200mm DI-K9 pipe from Thuppanad Jn to 2LL OHSR at Kalladikode TB Jn &Siruvani canal jn to 2LL OHSR at Edakurussi along NH 966(Risk&Cost work)

Project KIIFB 2017-18-CWSS to Karimba,Kongad and Mundur(part) panchayaths in Palakkad district-Laying 200mm DI-K9 pipe from Thuppanad Jn to 2LL OHSR at Kalladikode TB Jn &Siruvani canal jn to 2LL OHSR at Edakurussi along NH 966(Risk&Cost work)
Project Code PKDKIIFB1118667P3
Type Package
Main Project KIIFB 2017-18-Comprehensive drinking water scheme to Karimba and Kongad panchayaths in Mannarkkad and palakkad taluk in Palakkad Dt.-Phase I-Construction of pumphouse and control room, supplying and laying of raw water pumping main of 450mm dia DI K9 pipe for a length of 920m, construction, trial running and maintenance of 12 MLD WTP, construction of drainage pond at WTP premise, supplying and erection of RW and CW pumpsets and transformers.
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB 2017-18-CWSS to Karimba,Kongad and Mundur(part) panchayaths in Palakkad district-Laying 200mm DI-K9 pipe from Thuppanad Jn to 2LL OHSR at Kalladikode TB Jn &Siruvani canal jn to 2LL OHSR at Edakurussi along NH 966(Risk&Cost work)
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 5263874
TS Number TS/2021-2022/2021/41296
Technical specification Laying 200mm DI-K9 Pipe
Contractor Noufal PK (Mob: 9207133135)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
09 Feb 2022 Pending Pending Road Cut Related Risk Laying the CWGM through NH-966 where the road is under refurbishment by PWD(NH).therefore coordination with the PWD dept is essential to commence the work. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/01/2022
Scheduled date of Completion as per agreement 20 Feb 2022
Expected date of Completion 30/11/2022

Processing Dates

TS Date 10 Dec 2021
Estimate Approval 10 Dec 2021
NIT Approval 10 Jan 2022
Tender Closing 14 Jan 2022
Technichal Pre-Qualification 15 Jan 2022
Price bid opening 15 Jan 2022

Approval Dates

Workorder Date 17 Jan 2022
NA 21 Jan 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Project Dn EE
Date: 13/03/2023

Work has been completed | 100% Completed

Pipelaying completed under condractors scope. .

Palakkad Proj AE 3
Date: 10/03/2023

Work in progress | 91% Completed

Pipelaying completed 91% only. Chamber works & interlinking completed. Balance laying kept on hold due to NH-966 widening works at Edakurissi area. ULCCS's Road formation work& Bridge construction creating hindrance to KWA works. Though road cutting permission obtained, pipelaying kept on hold till the completion of earth work by PWD..