- Home
- AMRUT 2.0 WSS to Cherpulassery Muncipali...
AMRUT 2.0 WSS to Cherpulassery Muncipality supplying,laying ,testing ,commissioning & maintanance of Distribution lines ,providing FHTC's -2300 nos including Road restoration
Project |
AMRUT 2.0 WSS to Cherpulassery Muncipality supplying,laying ,testing ,commissioning & maintanance of Distribution lines ,providing FHTC's -2300 nos including Road restoration |
Project Code |
PKDAMRUT112214101 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT 2.0 WSS to Cherpulassery Muncipality supplying,laying ,testing ,commissioning & maintanance of Distribution lines ,providing FHTC's -2300 nos including Road restoration |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
106307000
|
AS Number |
GO (RT)no.2906/2022/LSGD |
TS Amount (Rs) |
99230000 |
TS Number |
WRD/KWA/-CE(NR)/EST_TS/1252/2022_26_1_1 |
Total Bill Submitted (Rs) |
43123190 |
Total Bill Paid (Rs) |
43123190 |
Population Benefitted |
2300 |
Capacity in MLD |
22.00 |
Actual Project Completion Date |
04 Nov 2024 |
Coverage |
CHERPULASSERY MUNCIPALITY |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2.0 WSS to Cherpulassery Muncipality supplying,laying ,testing ,commissioning & maintanance of Distribution lines ,providing FHTC's -2300 nos including Road restoration |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
Road restoration work on going. Interconnection & linking work on going.House connection 165 nos & Geo tagged 146 nos,13.439/ 15 km completed . |
Palakkad Proj Dn AE 4 |
|
06 May 2024 |
Road restoration work on going. Interconnection & linking work on going.House connection 165 nos & Geo tagged 146 nos,13.439/ 15 km completed . |
Palakkad Proj Dn AE 4 |
|
04 May 2024 |
Road restoration work on going. Interconnection & linking work on going.House connection 165 nos & Geo tagged 146 nos,13.439/ 15 km completed . |
Palakkad Proj Dn AE 4 |
|
03 May 2024 |
Road restoration work on going. House connection 165 nos & Geo tagged 142 nos,13.439/ 15 km completed . |
Palakkad Proj Dn AE 4 |
|
02 May 2024 |
Road restoration work on going. House connection 165 nos & Geo tagged 139 nos,13.439/ 15 km completed . |
Palakkad Proj Dn AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
05/05/2023 |
Scheduled date of Completion of the Project |
05 Nov 2023 |
Expected date of Completion |
31/05/2024 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
24 Jan 2023 |