Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-Phase 2-Providing remaining FTHC in Mankada pt from the scheme CARWSS to Moorkanad and adjoining villages.-Package V.

Project JJM-Phase 2-Providing remaining FTHC in Mankada pt from the scheme CARWSS to Moorkanad and adjoining villages.-Package V.
Project Code MLPJJM09218974P5
Type Package
Main Project JJM-Phase 2-2021-2022 -Providing remaining FTHC in Mankada pt from the scheme CARWSS to Moorkanad and adjoining villages.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Package V.- 1617 FHTC
Status On-going
District Malappuram
Executing Office Mankada PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 64800000
TS Number Reg.No.16139/2021-2022
Technical specification The project includes providing 1617 FHTC and laying of 20 KM distribution lines

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/04/2022
Scheduled date of Completion as per agreement 16 Dec 2022
Expected date of Completion 08/04/2023

Processing Dates

TS Date 23 Dec 2021
Estimate Approval 15 Dec 2021
NIT Approval 23 Dec 2021
Tender Closing 18 Mar 2022
Technichal Pre-Qualification 22 Mar 2022
Price bid opening 22 Mar 2022

Approval Dates

Workorder Date 09 Apr 2022
NA 13 Apr 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mankada AE
Date: 29/06/2024

Work in progress | 74% Completed

Total 871 FHTCs completed ,out of which 871 FHTC geotagged, work is completed.

Mankada AE
Date: 15/06/2024

Work in progress | 74% Completed

All pipe line laying work completed. Total 1254 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme. .