Project | Jal Jeevan Mission-Kasaragod District-West Eleri Panchayath-WSS to West Eleri-Phase II-Laying distribution system and providing FHTC in Paramba and Mouveni |
---|---|
Project Code | KGDJJM08202965P6 |
Type | Package |
Main Project | Jal Jeevan Mission- Kasaragod District- West Eleri Panchayath- WSS to West Eleri Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Laying distribution system and providing FHTC in Paramba and Mouveni |
Status | On-going |
District | Kasaragod |
Executing Office | Cheruvathoor Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 40100000 |
TS Number | 18001/2021-2022 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | 15 Jun 2022 |
Expected date of Completion | 28/06/2024 |
TS Date | 14 Jan 2022 |
---|---|
Estimate Approval | 14 Jan 2022 |
Workorder Date | 16 Feb 2022 |
---|
Cheruvathur AE |
Date: 28/06/2024 |
Work in progress | 68% Completed
Pipe laying completed, 55 numbers FHTC given. 250 numbers HTC given.
Cheruvathur AE |
Date: 24/06/2024 |
Work in progress | 68% Completed
Pipe laying completed, 55 numbers FHTC given. 250 numbers HTC given.