| Project | Replacement of damaged pipes-RWSS to Chakkakanam-Replacement of damaged pumping main and partial replacement of Distribution system |
|---|---|
| Project Code | IDKGOK05153989P1 |
| Type | Package |
| Main Project | 19-Replacement of damaged pipes-RWSS to Chakkakanam-Replacement of damaged pumping main and partial replacement of Distribution system |
| Funding Agency | GOK |
| Category | State plan |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | Replacement of damaged pipes-RWSS to Chakkakanam-Replacement of damaged pumping main and partial replacement of Distribution system |
| Status | Completed |
| District | Idukki |
| Executing Office | Thodupuzha PH Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | |
| TS Number | |
| Technical specification | Replacement of damaged pumping main and partial replacement of Distribution system |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 07/06/2016 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 06/10/2016 |
| AS Date | 28 May 2015 |
|---|---|
| TS Date | 10 Jun 2015 |
| Workorder Date | 17 May 2016 |
|---|---|
| NA | 07 Jul 2016 |
| Thodupuzha PH Dn EE |
| Date: 03/02/2021 |
| Thodupuzha PH Dn EE |
| Date: 25/11/2020 |
Work has been completed | 100% Completed
Completed.