| Project | Deposit Work -2021-22- RWSS to Kudayathoor - Extension/ Replacement of pipelines in various Wards of Kudayathoor Grama Panchayath. |
|---|---|
| Project Code | IDKDEPO032210430P1 |
| Type | Package |
| Main Project | Deposit Work -2021-22- RWSS to Kudayathoor - Extension/ Replacement of pipelines in various Wards of Kudayathoor Grama Panchayath. |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | Deposit Work -2021-22- RWSS to Kudayathoor - Extension/ Replacement of pipelines in various Wards of Kudayathoor Grama Panchayath. |
| Status | On-going |
| District | Idukki |
| Executing Office | Thodupuzha PH Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 684000 |
| TS Number | 168/2022-2023 |
| Technical specification | Extension/ Replacement of pipelines |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 13/05/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 31 Dec 2022 |
| Expected date of Completion | 30/11/2022 |
| TS Date | 05 Apr 2022 |
|---|---|
| Estimate Approval | 05 Apr 2022 |
| NIT Approval | 08 Apr 2022 |
| Tender Closing | 02 Aug 2022 |
| Technichal Pre-Qualification | 04 Aug 2022 |
| Price bid opening | 04 Aug 2022 |
| Workorder Date | 03 Sep 2022 |
|---|---|
| NA | 12 Sep 2022 |
| Thodupuzha PH Dn EE |
| Date: 06/03/2023 |
Work has been completed | 100% Completed
work has been completed.
| Thodupuzha PH Dn EE |
| Date: 04/03/2023 |
Work has been completed | 100% Completed
work has been completed.