KIIFB Comprehensive Water Supply Scheme to Karimba, Kongad &Mundur (part ) Panchayaths.-Phase 1-Package II .Design,construction,commissioning & maintenance of 13 LL OHSR at Parakkal in Karimba panchayath, supplying , laying and testing and commissioing and trial running of clear water pumping mains and clear water gravity main to OHSR s construction of drainage pond at WTP premise, Supplying and erection of motor pumpsets including road restoration

Project KIIFB Comprehensive Water Supply Scheme to Karimba, Kongad &Mundur (part ) Panchayaths.-Phase 1-Package II .Design,construction,commissioning & maintenance of 13 LL OHSR at Parakkal in Karimba panchayath, supplying , laying and testing and commissioing and trial running of clear water pumping mains and clear water gravity main to OHSR s construction of drainage pond at WTP premise, Supplying and erection of motor pumpsets including road restoration
Project Code PKDKIIFB1118667P2
Type Package
Main Project KIIFB 2017-18-Comprehensive drinking water scheme to Karimba and Kongad panchayaths in Mannarkkad and palakkad taluk in Palakkad Dt.-Phase I-Construction of pumphouse and control room, supplying and laying of raw water pumping main of 450mm dia DI K9 pipe for a length of 920m, construction, trial running and maintenance of 12 MLD WTP, construction of drainage pond at WTP premise, supplying and erection of RW and CW pumpsets and transformers.
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB Comprehensive Water Supply Scheme to Karimba, Kongad &Mundur (part ) Panchayaths.-Phase 1-Package II .Design,construction,commissioning & maintenance of 13 LL OHSR at Parakkal in Karimba panchayath, supplying , laying and testing and commissioing and trial running of clear water pumping mains and clear water gravity main to OHSR s construction of drainage pond at WTP premise, Supplying and erection of motor pumpsets including road restoration
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 164800000
TS Number TS/2019-20/2020/2731
Technical specification .Design,construction,commissioning & maintenance of 13 LL OHSR at Parakkal in Karimba panchayath, supplying , laying and testing and commissioing and trial running of clear water pumping mains and clear water gravity main to OHSR s construction of drainage pond at WTP premise, Supplying and erection of motor pumpsets including road restoration
Contractor Joseph John (Mob: 9447267097)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
02 Feb 2022 Pending Pending Land Related Risk Sri joseph jhon contractor wasTerminated from the work .The balance work want to re arrange in Risk and cost as per the direction from SE,Termination order no:KWA/PHC/PKD/KIIFB-KARIBA Dtd:01-01-2022 No comments available. Pending
05 Nov 2021 Pending Pending Land Related Risk The work completion period expired on 05/11/201 but the contractor not executed the supplementary agreement .From this office this was intimated three times to the contractor by email,phone,&post .The contractor give writ petition to Honorable high court for leaving from this work.The contractor not supplied the 70% of Pipes for this work No comments available. Pending
01 Jul 2021 Pending Pending Land Related Risk The land available for the construction of 13.00LL OHSR is under dispute due to local issues. No comments available. Pending
01 Jan 2021 22 Sep 2021 Pending Land Related Risk 3 cents of additional land required for construction of 13.00LL OHSR. MLA meeting conviened on 05/07/21 & direction has been issued for LA. Advance possetion from 3 parties were requested under pending to start the work AS per the direction of SE THE SET out of work done with available land by increasing side wall height and contractor was asked to submitt the design of tank accordingly Solved

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 19/09/2020
Scheduled date of Completion as per agreement 05 Nov 2021
Expected date of Completion 05/06/2022

Processing Dates

TS Date 18 Feb 2020
Estimate Approval 18 Feb 2020
NIT Approval 18 Feb 2020
Tender Closing 18 Mar 2020
Technichal Pre-Qualification 04 Jun 2020
Price bid opening 07 Mar 2020

Approval Dates

Workorder Date 06 Nov 2020
NA 24 Nov 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Proj AE 3
Date: 31/01/2024

Work in progress | 12% Completed

Vide order no-KWA/PHC/PKD/KIIFB/KARIMBA dt.01-01-2022 of SE,PHC Palakkad the contract has been terminated & the part work of laying 200mm DI k9 along NH966 fom Thuppanad to Kalladikkode(2km) has been arranged under the risk & cost of terminated work work. Balance scope of work has to be arranged under risk & cost of the contractor subjected to the final verdict of the Hon. HC of Kerala..

Palakkad Proj AE 3
Date: 30/01/2024

Work in progress | 12% Completed

Vide order no-KWA/PHC/PKD/KIIFB/KARIMBA dt.01-01-2022 of SE,PHC Palakkad the contract has been terminated & the part work of laying 200mm DI k9 along NH966 fom Thuppanad to Kalladikkode(2km) has been arranged under the risk & cost of terminated work work. Balance scope of work has to be arranged under risk & cost of the contractor subjected to the final verdict of the Hon. HC of Kerala. .