KIIFB Comprehensive Water Supply Scheme to Karimba, Kongad &Mundur (part ) Panchayaths.-Phase 1-Package II .Design,construction,commissioning & maintenance of 13 LL OHSR at Parakkal in Karimba panchayath, supplying , laying and testing and commissioing and trial running of clear water pumping mains and clear water gravity main to OHSR s construction of drainage pond at WTP premise, Supplying and erection of motor pumpsets including road restoration
Project |
KIIFB Comprehensive Water Supply Scheme to Karimba, Kongad &Mundur (part ) Panchayaths.-Phase 1-Package II .Design,construction,commissioning & maintenance of 13 LL OHSR at Parakkal in Karimba panchayath, supplying , laying and testing and commissioing and trial running of clear water pumping mains and clear water gravity main to OHSR s construction of drainage pond at WTP premise, Supplying and erection of motor pumpsets including road restoration |
Project Code |
PKDKIIFB1118667P2 |
Type |
Package |
Main Project |
KIIFB 2017-18-Comprehensive drinking water scheme to Karimba and Kongad panchayaths in Mannarkkad and palakkad taluk in Palakkad Dt.-Phase I-Construction of pumphouse and control room, supplying and laying of raw water pumping main of 450mm dia DI K9 pipe for a length of 920m, construction, trial running and maintenance of 12 MLD WTP, construction of drainage pond at WTP premise, supplying and erection of RW and CW pumpsets and transformers.
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB Comprehensive Water Supply Scheme to Karimba, Kongad &Mundur (part ) Panchayaths.-Phase 1-Package II .Design,construction,commissioning & maintenance of 13 LL OHSR at Parakkal in Karimba panchayath, supplying , laying and testing and commissioing and trial running of clear water pumping mains and clear water gravity main to OHSR s construction of drainage pond at WTP premise, Supplying and erection of motor pumpsets including road restoration |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
164800000 |
TS Number |
TS/2019-20/2020/2731 |
Technical specification |
.Design,construction,commissioning & maintenance of 13 LL OHSR at Parakkal in Karimba panchayath, supplying , laying and testing and commissioing and trial running of clear water pumping mains and clear water gravity main to OHSR s construction of drainage pond at WTP premise, Supplying and erection of motor pumpsets including road restoration |
Contractor |
Joseph John (Mob: 9447267097) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
02 Feb 2022 |
Pending |
Pending |
Land Related Risk |
Sri joseph jhon contractor wasTerminated from the work .The balance work want to re arrange in Risk and cost as per the direction from SE,Termination order no:KWA/PHC/PKD/KIIFB-KARIBA Dtd:01-01-2022 |
No comments available. |
Pending |
05 Nov 2021 |
Pending |
Pending |
Land Related Risk |
The work completion period expired on 05/11/201 but the contractor not executed the supplementary agreement .From this office this was intimated three times to the contractor by email,phone,&post .The contractor give writ petition to Honorable high court for leaving from this work.The contractor not supplied the 70% of Pipes for this work |
No comments available. |
Pending |
01 Jul 2021 |
Pending |
Pending |
Land Related Risk |
The land available for the construction of 13.00LL OHSR is under dispute due to local issues. |
No comments available. |
Pending |
01 Jan 2021 |
22 Sep 2021 |
Pending |
Land Related Risk |
3 cents of additional land required for construction of 13.00LL OHSR. MLA meeting conviened on 05/07/21 & direction has been issued for LA. Advance possetion from 3 parties were requested under pending to start the work |
AS per the direction of SE THE SET out of work done with available land by increasing side wall height and contractor was asked to submitt the design of tank accordingly |
Solved |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
19/09/2020 |
Scheduled date of Completion as per agreement |
05 Nov 2021 |
Expected date of Completion |
05/06/2022 |
Processing Dates
TS Date |
18 Feb 2020 |
Estimate Approval |
18 Feb 2020 |
NIT Approval |
18 Feb 2020 |
Tender Closing |
18 Mar 2020 |
Technichal Pre-Qualification |
04 Jun 2020 |
Price bid opening |
07 Mar 2020 |
Approval Dates
Workorder Date |
06 Nov 2020 |
NA |
24 Nov 2020 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Palakkad Proj AE 3 |
Date: 31/01/2024 |
Work in progress | 12% Completed
Vide order no-KWA/PHC/PKD/KIIFB/KARIMBA dt.01-01-2022 of SE,PHC Palakkad the contract has been terminated & the part work of laying 200mm DI k9 along NH966 fom Thuppanad to Kalladikkode(2km) has been arranged under the risk & cost of terminated work work. Balance scope of work has to be arranged under risk & cost of the contractor subjected to the final verdict of the Hon. HC of Kerala..
Palakkad Proj AE 3 |
Date: 30/01/2024 |
Work in progress | 12% Completed
Vide order no-KWA/PHC/PKD/KIIFB/KARIMBA dt.01-01-2022 of SE,PHC Palakkad the contract has been terminated & the part work of laying 200mm DI k9 along NH966 fom Thuppanad to Kalladikkode(2km) has been arranged under the risk & cost of terminated work work. Balance scope of work has to be arranged under risk & cost of the contractor subjected to the final verdict of the Hon. HC of Kerala.
.