Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Desamangalam Panchayath-Providing Distribution Network and FHTC to Desamangalam Panchayath

Project Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Desamangalam Panchayath-Providing Distribution Network and FHTC to Desamangalam Panchayath
Project Code TCRJJM052213581P1
Type Package
Main Project Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Desamangalam Panchayath-Providing Distribution Network and FHTC to Desamangalam Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Desamangalam Panchayath-Providing Distribution Network and FHTC to Desamangalam Panchayath
Status On-going
District Thrissur
Executing Office Nattika Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 367900000
TS Number WRD/KWA-CEP/EST-TS/135/2022-5_1_1
Technical specification Providing Distribution Network and FHTC to Desamangalam Panchayath

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 14/02/2023
Scheduled date of Completion as per agreement 16 Jan 2024
Expected date of Completion 14/02/2024

Processing Dates

TS Date 27 Oct 2022
Estimate Approval 27 Oct 2022
Tender Closing 23 Nov 2022
Technichal Pre-Qualification 25 Nov 2022
Price bid opening 24 Dec 2022

Approval Dates

Workorder Date 16 Jan 2023
NA 23 Jan 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nattika Project Dn
Date: 28/06/2024

Work in progress | 57% Completed

81680m Pipeline laid (200 DI-2435m,160 mm HDPE pipe pn10-2094m, 160 mm HDPE pipe pn8-1944m,110 mm HDPE pipe pn 10-10409m,HDPE pipe,110 mm HDPE pipe pn 8-4895m,90 HDPE pipe pn 10-17473m,90 HDPE pipe pn 8-12828m,90PVC class3-2435m, 75PVC pipe class 5-6791, 75 mm PVC pipe class 4-2036,75 mm PVC pipe class 3-1544m, 63 mm PVC pipe class 5-4211,63 mm PVC pipe class 4-4152,63 mm PVC pipe class 3-3292 mm ,50mm PVC pipe class 5-1260m,50 mm PVC pipe class 4-469m,50 mm PVC pipe class 3-2184m,40 PVC pipe -1363m). Geo Tagging = 1966/3047 Nos. HTC - 1976/3047 Nos.,Road Restoration-39823m/102261m.

Nattika Project Dn
Date: 27/06/2024

Work in progress | 57% Completed

81680m Pipeline laid (200 DI-2435m,160 mm HDPE pipe pn10-2094m, 160 mm HDPE pipe pn8-1944m,110 mm HDPE pipe pn 10-10409m,HDPE pipe,110 mm HDPE pipe pn 8-4895m,90 HDPE pipe pn 10-17473m,90 HDPE pipe pn 8-12828m,90PVC class3-2435m, 75PVC pipe class 5-6791, 75 mm PVC pipe class 4-2036,75 mm PVC pipe class 3-1544m, 63 mm PVC pipe class 5-4211,63 mm PVC pipe class 4-4152,63 mm PVC pipe class 3-3292 mm ,50mm PVC pipe class 5-1260m,50 mm PVC pipe class 4-469m,50 mm PVC pipe class 3-2184m,40 PVC pipe -1363m). Geo Tagging = 1966/3047 Nos. HTC - 1976/3047 Nos.,Road Restoration-39823m/102261m.