Project | JJM- Phase II -Parappukara Grama panchayath -Total station survey of Distribution line and Pumping main |
---|---|
Project Code | TCRJJM052211020P1 |
Type | Package |
Main Project | JJM - Parappukkara Grama Panchayath -Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM- Phase II -Parappukara Grama panchayath -Total station survey of Distribution line and Pumping main |
Status | On-going |
District | Thrissur |
Executing Office | Irinjalakkuda PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 390000 |
TS Number | TS/2022-2023/2022/21358 Dated: 02-06-2022 |
Technical specification | JJM- Phase II -Parappukara Grama panchayath -Total station survey of Distribution line and Pumping main |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 02/06/2022 |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | 30/06/2022 |
TS Date | 02 Jun 2022 |
---|---|
Estimate Approval | 02 Jun 2022 |
NIT Approval | 02 Jun 2022 |
Tender Closing | 06 Jun 2022 |
Price bid opening | 06 Jun 2022 |
Workorder Date | 23 Jun 2022 |
---|
Irinjalakuda AEE |
Date: 22/08/2022 |
Work has been completed | 100% Completed
work completed on 30.06.2022 and bill under preparation.
Irinjalakuda AE |
Date: 20/08/2022 |
Work has started | 0% Completed
Work order issued .