| Project | NABARD - Kottiyoor,Kelakam and Kanichar Panchayath- Supply and erection of Pumpsets - Package V Part II |
|---|---|
| Project Code | KNRNABARD12173151P8 |
| Type | Package |
| Main Project | NABARD -RIDF-XXIII- WSS to Kottiyoor, Kelakam and Kanichar Panchayaths in Iritty Taluk of Kannur District - Phase I |
| Funding Agency | NABARD |
| Category | NABARD |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-98 (01) |
| Description | NABARD - Kottiyoor,Kelakam and Kanichar Panchayath- Supply and erection of Pumpsets - Package V Part II |
| Status | On-going |
| District | Kannur |
| Executing Office | Koothuparamba Project Sn No2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 5473626 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/14259/2022_5_1_1 |
| Technical specification | Supply and erection of Pumpsets |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/09/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 30 Nov 2023 |
| Expected date of Completion | 25/03/2024 |
| TS Date | 11 May 2023 |
|---|---|
| Estimate Approval | 11 May 2023 |
| NIT Approval | 11 May 2023 |
| Tender Closing | 22 May 2023 |
| Price bid opening | 23 May 2023 |
| Workorder Date | 08 Aug 2023 |
|---|---|
| NA | 22 Aug 2023 |
| Koothuparamba Proj AE 2 |
| Date: 13/03/2024 |
Work has started | 0% Completed
work dropped.
| Koothuparamba Proj AE 2 |
| Date: 04/03/2024 |
Work in progress | 1% Completed
Pump testing done. Awaiting delivery.