Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath-- 4th SLSSC- Part I - Providing balance FHTCS-General Civil Work

Project Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath-- 4th SLSSC- Part I - Providing balance FHTCS-General Civil Work
Project Code TCRJJM022214760P1
Type Package
Main Project Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath-- 4th SLSSC
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath-- 4th SLSSC- Part I - Providing balance FHTCS-General Civil Work
Status On-going
District Thrissur
Executing Office Guruvayur PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 2250000
TS Number WRD/KWA-CE(CR)/EST_TS/17646/2023_5_1_1 Dated: 01-08-2023
Technical specification Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath-- 4th SLSSC- Part I - Providing balance FHTCS-General Civil Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 16/08/2023
Scheduled date of Completion as per agreement 15 Nov 2023
Expected date of Completion 31/07/2024

Processing Dates

TS Date 01 Aug 2023
Estimate Approval 01 Aug 2023
NIT Approval 02 Aug 2023
Tender Closing 09 Aug 2023
Technichal Pre-Qualification 09 Aug 2023
Price bid opening 10 Aug 2023

Approval Dates

Workorder Date 16 Aug 2023
NA 26 Aug 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thrissur PH Dn EE
Date: 01/07/2024

Work in progress | 13% Completed

Work Ongoing. 25 Nos. Tagged. Bill submitted..

Guruvayur PH Sn AE
Date: 29/06/2024

Work in progress | 13% Completed

Work Ongoing. 25 Nos. Tagged. Bill submitted. .