| Project | PACKAGE VII- CONSTRUCTION OF 11 LL CAPACITY OHSR AT AYITHARA COLONY , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN MANGATTIDAM GRAMA PANCHAYATH |
|---|---|
| Project Code | KNRJJM022213306P7 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Construction of 11 LL capacity OHSR at Ayithara colony ,supplying ,laying and commissioning distribution system , Providing 7706 Nos FHTCs |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 593600000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/7528/2022_26_1_1 |
| Technical specification | Construction of 11 LL capacity OHSRat Ayithara colony ,supplying ,laying and commissioning distribution system , Providing 7706 Nos FHTCs |
| Contractor | Baburaj P K (Mob: 9447152707) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 22/06/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 21 Jun 2024 |
| Expected date of Completion | 31/12/2026 |
| TS Date | 02 Nov 2022 |
|---|---|
| Estimate Approval | 02 Nov 2022 |
| NIT Approval | 02 Dec 2022 |
| Tender Closing | 10 Apr 2023 |
| Technichal Pre-Qualification | 22 Nov 2022 |
| Price bid opening | 12 Apr 2023 |
| Workorder Date | 26 May 2023 |
|---|---|
| NA | 12 Jun 2023 |
| Mattannur Project Sn 2 AE |
| Date: 22/04/2026 |
Work in progress | 96% Completed
Total Distribution is 209 km. 209 km pipe has supplied. 217 km pipe laying completed. 6570 nos HTC completed. In this 4423nos. FHTC given. Construction of 11LL capacity OHSR at Ayithara completed.Trial running-distribution main line charging,water supply and testing work in progress,70% completed. Reservoir compound wall completed,Plastering work also completed. Road restoration work also in progress.Ayithara-Goshala Road 500m tarring completed.Due to Ayppanthode bridge construction utility shifting work completed.Irish concrete completed at Ayithara-Neerveli PWD Road. Lsgd road restoration also in progress.,8 roads completed.
| Mattannur Project Sn 2 AE |
| Date: 08/04/2026 |
Work in progress | 96% Completed
Total Distribution is 209 km. 209 km pipe has supplied. 215 km pipe laying completed. 6570 nos HTC completed. In this 4364nos. FHTC given. Construction of 11LL capacity OHSR at Ayithara completed.Trial running-distribution main line charging,water supply and testing work in progress,70% completed. Reservoir compound wall completed,Plastering work also completed. Road restoration work also in progress.Ayithara-Goshala Road 500m tarring completed.Due to Ayppanthode bridge construction utility shifting work completed.Irish concrete completed at Ayithara-Neerveli PWD Road. Lsgd road restoration also in progress.,5 roads completed.