Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

PACKAGE VII- CONSTRUCTION OF 11 LL CAPACITY OHSR AT AYITHARA COLONY , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN MANGATTIDAM GRAMA PANCHAYATH

Project PACKAGE VII- CONSTRUCTION OF 11 LL CAPACITY OHSR AT AYITHARA COLONY , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN MANGATTIDAM GRAMA PANCHAYATH
Project Code KNRJJM022213306P7
Type Package
Main Project JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of 11 LL capacity OHSR at Ayithara colony ,supplying ,laying and commissioning distribution system , Providing 7706 Nos FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 593600000
TS Number WRD/KWA-CE(NR)/EST_TS/7528/2022_26_1_1
Technical specification Construction of 11 LL capacity OHSRat Ayithara colony ,supplying ,laying and commissioning distribution system , Providing 7706 Nos FHTCs
Contractor Baburaj P K (Mob: 9447152707)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/06/2023
Scheduled date of Completion as per agreement 21 Jun 2024
Expected date of Completion 31/12/2026

Processing Dates

TS Date 02 Nov 2022
Estimate Approval 02 Nov 2022
NIT Approval 02 Dec 2022
Tender Closing 10 Apr 2023
Technichal Pre-Qualification 22 Nov 2022
Price bid opening 12 Apr 2023

Approval Dates

Workorder Date 26 May 2023
NA 12 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 22/04/2026

Work in progress | 96% Completed

Total Distribution is 209 km. 209 km pipe has supplied. 217 km pipe laying completed. 6570 nos HTC completed. In this 4423nos. FHTC given. Construction of 11LL capacity OHSR at Ayithara completed.Trial running-distribution main line charging,water supply and testing work in progress,70% completed. Reservoir compound wall completed,Plastering work also completed. Road restoration work also in progress.Ayithara-Goshala Road 500m tarring completed.Due to Ayppanthode bridge construction utility shifting work completed.Irish concrete completed at Ayithara-Neerveli PWD Road. Lsgd road restoration also in progress.,8 roads completed.

Mattannur Project Sn 2 AE
Date: 08/04/2026

Work in progress | 96% Completed

Total Distribution is 209 km. 209 km pipe has supplied. 215 km pipe laying completed. 6570 nos HTC completed. In this 4364nos. FHTC given. Construction of 11LL capacity OHSR at Ayithara completed.Trial running-distribution main line charging,water supply and testing work in progress,70% completed. Reservoir compound wall completed,Plastering work also completed. Road restoration work also in progress.Ayithara-Goshala Road 500m tarring completed.Due to Ayppanthode bridge construction utility shifting work completed.Irish concrete completed at Ayithara-Neerveli PWD Road. Lsgd road restoration also in progress.,5 roads completed.