Status Date |
Overall Project Status |
Project Officer |
Contact |
23 Apr 2024 |
600 mm Flow meter fixing at the outlet of OHSR 9 LL, over flow pipe and scour pipe fixing completed. Out of 7000 FHTCs, around 1682 FHTCs and 2209 HTCs done ,40 km of 90 mm PVC laid completed , 40 km of 160 mm PVC laid out of 25 km, 4 km of 110 mm PVC laid completed,24.400 km of 160 mm PVC laid completed, 2.6 km 200 mm DI laid completed,2.6 km of 250 mm DI laid completed,1.5 km of 300 mm DI laid out of 300 m,650 km of 450 mm DI laid completed, 1 km of 600 mm DI laid completed 600 mm Flow meter fixing at the outlet of OHSR 9 LL, Over flow pipe and scour pipe fixing completed. |
Alappuzha Project Dn PM |
|
06 Apr 2024 |
600 mm Flow meter fixing at the outlet of OHSR 9 LL, over flow pipe and scour pipe fixing completed. Out of 7000 FHTCs, around 1682 FHTCs and 2209 HTCs done ,40 km of 90 mm PVC laid completed , 40 km of 160 mm PVC laid out of 25 km, 4 km of 110 mm PVC laid completed,24.400 km of 160 mm PVC laid completed, 2.6 km 200 mm DI laid completed,2.6 km of 250 mm DI laid completed,1.5 km of 300 mm DI laid out of 300 m,650 km of 450 mm DI laid completed, 1 km of 600 mm DI laid completed 600 mm Flow meter fixing at the outlet of OHSR 9 LL, Over flow pipe and scour pipe fixing completed. |
Alappuzha Project Dn PM |
|
20 Mar 2024 |
600 mm Flow meter fixing at the outlet of OHSR 9 LL, over flow pipe and scour pipe fixing completed. Out of 7000 FHTCs, around 1682 FHTCs and 2209 HTCs done ,40 km of 90 mm PVC laid completed , 40 km of 160 mm PVC laid out of 25 km, 4 km of 110 mm PVC laid completed,24.400 km of 160 mm PVC laid completed, 2.6 km 200 mm DI laid completed,2.6 km of 250 mm DI laid completed,1.5 km of 300 mm DI laid out of 300 m,650 km of 450 mm DI laid completed, 1 km of 600 mm DI laid completed 600 mm Flow meter fixing at the outlet of OHSR 9 LL, Over flow pipe and scour pipe fixing completed. |
Alappuzha Project Dn PM |
|
12 Feb 2024 |
600 mm Flow meter fixing at the outlet of OHSR 9 LL, over flow pipe and scour pipe fixing completed. Out of 7000 FHTCs, around 1682 FHTCs and 2209 HTCs done ,40 km of 90 mm PVC laid completed , 40 km of 160 mm PVC laid out of 25 km, 4 km of 110 mm PVC laid completed,24.400 km of 160 mm PVC laid completed, 2.6 km 200 mm DI laid completed,2.6 km of 250 mm DI laid completed,1.5 km of 300 mm DI laid out of 300 m,650 km of 450 mm DI laid completed, 1 km of 600 mm DI laid completed 600 mm Flow meter fixing at the outlet of OHSR 9 LL, Over flow pipe and scour pipe fixing completed. |
Alappuzha Project Dn PM |
|
29 Jan 2024 |
600 mm Flow meter fixing at the outlet of OHSR 9 LL, Over flow pipe and scour pipe fixing completed. Out of 7000 FHTCs, around 1682 FHTCs and 2209 HTCs done ,40 km of 90 mm PVC laid completed , 40 km of 160 mm PVC laid out of 25 km, 4 km of 110 mm PVC laid completed,24.400 km of 160 mm PVC laid completed, 2.6 km 200 mm DI laid completed,2.6 km of 250 mm DI laid completed,1.5 km of 300 mm DI laid out of 300 m,650 km of 450 mm DI laid completed, 1 km of 600 mm DI laid completed 600 mm Flow meter fixing at the outlet of OHSR 9 LL, Over flow pipe and scour pipe fixing completed. Out of 7000 FHTCs, around 1682 FHTCs and 2209 HTCs done ,40 km of 90 mm PVC laid completed , 40 km of 160 mm PVC laid out of 25 km, 4 km of 110 mm PVC laid completed,24.400 km of 160 mm PVC laid completed, 2.6 km 200 mm DI laid completed,2.6 km of 250 mm DI laid completed,1.5 km of 300 mm DI laid out of 300 m,650 km of 450 mm DI laid completed, 1 km of 600 mm DI laid completed |
Alappuzha Project Dn PM |
|