Project | JJM - WSS toThriprangodu, Mangalam, Purathur, Thalakkad and Vettom Panchayaths |
---|---|
Project Code | MLPJJM092112039 |
Type | Main project |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | 37 MLD WTP, Raw water pumping main, Distribution Net work, OHSRs, Electro- mechanical works, FHTCs |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
AS Amount (Rs) | 3440000000 |
AS Number | GO/Rt No 489/2021 |
TS Amount (Rs) | |
TS Number | |
Total Bill Submitted (Rs) | 241873093 |
Total Bill Paid (Rs) | 241873093 |
Population Benefitted | 150000 |
Capacity in MLD | 37.00 |
Actual Project Completion Date | Date is not specified |
Coverage | Thrprangodu, Mangalam, Purathur, Thalakkad and Vettom Panchayaths |
No. | Project Name | Location | View |
---|---|---|---|
1 | . | Project Division Malappuram | |
2 | Package 10 - JJM - WSS to Thriprangode, Mangalam, Purathur, Thalakkad and Vettam GPs - Construction of 41 LL OHSR At BP Angadi In Thalakkad GP. | Project Division Malappuram | |
3 | Package - 11 - JJM -Thrprangodu, Mangalam, Purathur, Thalakkad and Vettom Panchayaths- Laying Clear Water Pumping Main to Thriprangode HL Area and Construction of 8 LL OHSR At Kolupalam in Thriprangode GP. | Project Division Malappuram | |
4 | Package - 12 - JJM -Thrprangodu, Mangalam, Purathur, Thalakkad and Vettom Panchayaths- Laying Distribution Networks and Providing FHTCs In Thriprangode HL Area. | Project Division Malappuram | |
5 | Package - 1 - JJM -Thrprangodu, Mangalam, Purathur, Thalakkad and Vettom Panchayaths- Laying Raw water Pumping Main from Colony Kadavu at Bharathapuzha to Annassery WTP | Project Division Malappuram | |
6 | Package - 2 - JJM -Thrprangodu, Mangalam, Purathur, Thalakkad and Vettom Panchayaths- Laying Clear Water Pumping Mains, construction of 37 MLD WTP, Reseviorrs and Electromechanical Works | Project Division Malappuram | |
7 | Package - 3 - WSS TO Thripangode, Mangalam, Purathur,Thalakkad and Vettom GPs-Providing Distribution Network and FHTCs in Thripangode, Mangalam And Purathur GPs | Project Division Malappuram | |
8 | Package - 4 - WSS TO Thripangode, Mangalam, Purathur,Thalakkad and Vettom GPs-Providing Distribution Network and FHTCs in VETTOM GP. | Project Division Malappuram | |
9 | Package - 5 - WSS TO Thripangode, Mangalam, Purathur,Thalakkad and Vettom GPs-Providing Distribution Network and FHTCs in Thalakkad GP, High Level | Project Division Malappuram | |
10 | Package - 6 - WSS TO Thripangode, Mangalam, Purathur,Thalakkad and Vettom GPs-Providing Distribution Network and FHTCs in Thalakkad GP, Low Level | Project Division Malappuram | |
11 | Package 7 - JJM-WSS to Thriprangode, Mangalam, Purathur, Thalakkad and Vettam GPs - Construction of 20 LL OHSR At Thrithallur in Purathur GP and Clear Water Pumping Main to 20 LL OHSR At Purathur GP - General Civil Work | Project Division Malappuram | |
12 | Package 9 - JJM WSS to Thriprangode, Mangalam, Purathur, Thalakkad and Vettam GPs - Construction of 5 LL OHSR At Thekkankuttur and Providing FHTCs in Thalakkad GP HL. Generala Civil Work | Project Division Malappuram |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Sep 2023 | In package 1, 9%- Pipe laying stopped due to heavy rain. Package 2, TS Obtained, Tendering work in progress. Package 3, 7%-Pipe laying work in progress. Package 4,5 and 6, Work awarded. Package 7and 8, TS Obtained. Tendering work in progress. Package 9, 3%- Footing Work Completed. | Malappuram Project Dn AE5 | |
03 Aug 2023 | In package 1, 9% - Pipe laying stopped due to heavy rain. Package 2, Revised estimate submitted. Package 3, 6% - Pipe laying work stopped due to heavy rain. Package 4 and 5, Work tendered. Package 6, work tendered and processing. Package 7 and 8, Estimate Submitted. Package 9, Work Awarded. | Malappuram Project Dn AE5 | |
22 Jul 2023 | In package 1, 9% - Pipe laying stopped due to heavy rain. Package 2, Revised estimate submitted. Package 3, 6% - Pipe laying work stopped due to heavy rain. Package 4 and 5, Work Awarded. Package 6, work tendered and processing. Package 7 and 8, Estimate Submitted. Package 9, Work Awarded. | Malappuram Project Dn AE5 | |
30 Jun 2023 | In package 1, 9%- Pipe laying stopped due to heavy rain. Package 2, Revised estimate submitted. Package 3, 5%- Pipe laying work in progress. Package 4 and 5, Work Awarded. Package 6, work tendered and processing. Package 7 and 8, Estimate Submitted. Package 9, Work Awarded. | Malappuram Project Dn AE5 | |
01 Jun 2023 | In Package 1, 8% - Pipe laying work In progress. Package 2, Revised estimate submitted. Package 3, 4%- DI and PE Pipes supplied. Package 4,5 and 6, work tendered and processing. Package 7 and 8, Estimate Submitted. Package 9, Work Awarded. | Malappuram Project Dn AE5 |
Date of start of Project | Date is not specified |
---|---|
Scheduled date of Completion of the Project | 30 Jul 2023 |
Expected date of Completion | 08/06/2024 |
AS Date | 18 Sep 2021 |
---|
Project Officers | View |
---|