JJM KODUVAYUR-JalJeevan Mission - CWSS to Koduvayur Panchayaths - Design,Construction Commissioning and maintenance of 3LL and 7LL OHSR in Koduvayur panchayath with approach roads, Supplying, Laying, Testing,commissioning and maintenance of Clear Water pumping Main to OHSRs,distribution net works in Koduvayur panchayath with providing FHTCs (4408Nos) supply and erection of Clear Water pumpsets including PWD and LSGD road restoration works.
JJM KODUVAYUR-JalJeevan Mission - CWSS to Koduvayur Panchayaths - Design,Construction Commissioning and maintenance of 3LL and 7LL OHSR in Koduvayur panchayath with approach roads, Supplying, Laying, Testing,commissioning and maintenance of Clear Water pumping Main to OHSRs,distribution net works in Koduvayur panchayath with providing FHTCs (4408Nos) supply and erection of Clear Water pumpsets including PWD and LSGD road restoration works.
Project Code
PKDJJM052215017
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-02
Description
JJM KODUVAYUR-JalJeevan Mission - CWSS to Koduvayur Panchayaths - Design,Construction Commissioning and maintenance of 3LL and 7LL OHSR in Koduvayur panchayath with approach roads, Supplying, Laying, Testing,commissioning and maintenance of Clear Water pumping Main to OHSRs,distribution net works in Koduvayur panchayath with providing FHTCs (4408Nos) supply and erection of Clear Water pumpsets including PWD and LSGD road restoration works.
JJM KODUVAYUR-JalJeevan Mission - CWSS to Koduvayur Panchayaths - Design,Construction Commissioning and maintenance of 3LL and 7LL OHSR in Koduvayur panchayath with approach roads, Supplying, Laying, Testing,commissioning and maintenance of Clear Water pumping Main to OHSRs,distribution net works in Koduvayur panchayath with providing FHTCs (4408Nos) supply and erection of Clear Water pumpsets including PWD and LSGD road restoration works.
Project Division Chittur
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
26 Jan 2024
Not Started | 26/01/2024
work not started ,Agreement Executed on 07.09.2023( wide no 30/2023-24/SE/PHC/PKD dtd 07.09.2023)