JJM -CWSSto Kuttippuram Thirunnavaya, Athavanad and Marakkara Panchayaths

Project JJM -CWSSto Kuttippuram Thirunnavaya, Athavanad and Marakkara Panchayaths
Project Code MLPJJM022212040
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM -CWSSto Kuttippuram Thirunnavaya, Athavanad and Marakkara Panchayaths- 12.00m dial well cum pump house at Chenganakadavu , kuttippuram, 48 MLD WTP at Kuttippuram, 19.00LL Sump and 24 LL OHSR at Kinfra Park Kuttippuram
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
AS Amount (Rs) 2210712000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 114000000
TS Number WRD/KWA-CE(NR)/EST_TS/1558/2022_5_1_1
Total Bill Submitted (Rs) 77193619
Total Bill Paid (Rs) 77193619
Population Benefitted 471302
Capacity in MLD 48.00
Actual Project Completion Date 31 Mar 2025
Coverage Kuttippuram , Marakkara , Athavanad, Thirunavaya and Kottakkal Muncipality
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Construction of 40 LL OHSR at Malayil Project Division Malappuram
2 Construction of 48.00 MLD WTP at Kuttippuram Project Division Malappuram
3 CWSS to Kuttippuram, Thirunnavaya, Athavanad and Marakkara Panchayaths-Construction of 12m dia Well cum pump house and laying of raw water pumping main Project Division Malappuram
4 Jal Jeevan Mission (JJM)-CWSS to Kuttippuram, Thirunnavaya, Athavanad and Marakkara Panchayaths-Package 2 Construction of Sump and OHSR at Kinfra Park and Clear Water Pumping mains Project Division Malappuram

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Feb 2024 Package 1 - Construction of 12m dia Well cum pump house and laying of 800mm DI raw water pumping main. - Construction of well steining progressing- 3.40 m RCC completed. 800mm pipe line received at site but PWD permission not obtained. Land for road to WTP site not obtained from Kuttippuram panchayath for deciding length and route of of raw water pumping main. Package 2 -Construction of Sump and OHSR at Kinfra Park and Clear Water Pumping mains.-work prrogggrressingg-750 mm , 700 mm , 400 mm and 200 mm DI Pipes received at site . This work includes construction of 19.00LL Sump and 24 LL OHSR at Kinfra Park Kuttippuram, 750mm pumping main from WTP to Sump at Kinfra, 700 mm Pumping to Malayil tank and pumping mains to nirappilal and kifra OHSR. . NHAI permission denied for pipe line crossing at Kanjippura junction. Footing work for sump cum OHSR completed and sump floor slab steel work progressing at Kinfra Park and Pipe line laying inside of Kifra park progressing 3. WTP work LOA issued. 4. 40 LL OHSR at malayil- work awarded but site not obtained from panchayaths Malappuram Project Dn AE2
07 Feb 2024 Package 1 - Construction of 12m dia Well cum pump house and laying of 800mm DI raw water pumping main. - Construction of well steining progressing. 800mm pipe line received at site but PWD permission not obtained. Land for road to WTP site not obtained from Kuttippuram panchayath for deciding length and route of of raw water pumping main. Package 2 -Construction of Sump and OHSR at Kinfra Park and Clear Water Pumping mains.-work prrogggrressingg-750 mm , 700 mm , 400 mm and 200 mm DI Pipes received at site . This work includes construction of 19.00LL Sump and 24 LL OHSR at Kinfra Park Kuttippuram, 750mm pumping main from WTP to Sump at Kinfra, 700 mm Pumping to Malayil tank and pumping mains to nirappilal and kifra OHSR. PWD permission denied in Kanjjippura- Moodal bypass for laying pipe line. NHAI permission denied for pipe line crossing at Kanjippura junction. Footing work for sump cum OHSR completed and sump floor slab steel work progressing at Kinfra Park and Pipe line laying inside of Kifra park progressing 3. WTP work Tender opened and under process 4. 40 LL OHSR at malayil- work awarded but site not obtained from panchayaths Malappuram Project Dn AE2
10 Jan 2024 Package 1 - Construction of 12m dia Well cum pump house and laying of 800mm DI raw water pumping main. - Construction of well progressing. 800mm pipe line received at site but PWD permission not obtained. Land for road to WTP site not obtained from Kuttippuram panchayath for deciding length and route of of raw water pumping main. Package 2 -Construction of Sump and OHSR at Kinfra Park and Clear Water Pumping mains.-work prrogggrressingg-750 mm , 700 mm , 400 mm and 200 mm DI Pipes received at site . This work includes construction of 19.00LL Sump and 24 LL OHSR at Kinfra Park Kuttippuram, 750mm pumping main from WTP to Sump at Kinfra, 700 mm Pumping to Malayil tank and pumping mains to nirappilal and kifra OHSR. PWD permission denied in Kanjjippura- Moodal bypass for laying pipe line. NHAI permission denied for pipe line crossing at Kanjippura junction. Footing work for sump cum OHSR progressing at Kinfra Park and Pipe line laying inside of Kifra park progressing 3. WTP work Tender opened and under process 4. 40 LL OHSR at malayil- work awarded but site not obtained from panchayaths Malappuram Project Dn AE2
08 Nov 2023 Package 1 - Construction of 12m dia Well cum pump house and laying of 800mm DI raw water pumping main. - ongoing. 800mm pipe line received at site but PWD permission not obtained. Land for road to WTP site not obtained from Kuttippuram panchayath for deciding length and route of of raw water pumping main. Package 2 -Construction of Sump and OHSR at Kinfra Park and Clear Water Pumping mains.-work prrogggrressingg-750 mm , 700 mm , 400 mm and 200 mm DI Pipes received at site . This work includes construction of 19.00LL Sump and 24 LL OHSR at Kinfra Park Kuttippuram, 750mm pumping main from WTP to Sump at Kinfra, 700 mm Pumping to Malayil tank and pumping mains to nirappilal and kifra OHSR. PWD permission denied in Kanjjippura- Moodal bypass for laying pipe line. NHAI permission denied for pipe line crossing at Kanjippura junction. Excavation for Sump ongoing at Kinfra Park and Pipe line laying work at kifra park progressing 3. WTP work Tendered 4. 40 LL OHSR at malayil- site not obtained from panchayaths Malappuram Project Dn AE2
12 Sep 2023 Package 1 - Construction of 12m dia Well cum pump house and laying of 800mm DI raw water pumping main. - ongoing. 800mm pipe line received at site but PWD permission not obtained. Land for road to WTP site not obtained from Kuttippuram panchayath for deciding length and route of of raw water pumping main. Package 2 -Construction of Sump and OHSR at Kinfra Park and Clear Water Pumping mains.-work prrogggrressingg-750 mm , 700 mm , 400 mm and 200 mm DI Pipes received at site . This work includes construction of 19.00LL Sump and 24 LL OHSR at Kinfra Park Kuttippuram, 750mm pumping main from WTP to Sump at Kinfra, 700 mm Pumping to Malayil tank and pumping mains to nirappilal and kifra OHSR. PWD permission denied in Kanjjippura- Moodal bypass for laying pipe line. NHAI permission denied for pipe line crossing at Kanjippura junction. Excavation for Sump ongoing at Kinfra Park and Pipe line laying work at kifra park progressing 3. WTP work Tendered 4. 40 LL OHSR at malayil- site not obtained from panchayaths Malappuram Project Dn AE2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/03/2023
Scheduled date of Completion of the Project 31 Mar 2024
Expected date of Completion 31/03/2025

Processing Dates

AS Date 23 Feb 2022
TS Date 16 Nov 2022

Other details