Project | JJM-Augmentation of ARWSS to Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths -Renovation to 10 mld WTP Pattoor, Supplying and Laying of Distribution lines and giving House connections in Nooranadu, Chunakkara, Palamel Thamarakkulam Panchayaths and providing FHTC |
---|---|
Project Code | ALPJJM08207717P1 |
Type | Package |
Main Project | JJM-Augmentation of ARWSS to Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths -Renovation to 10 mld WTP Pattoor, Supplying and Laying of Distribution lines and giving House connections in Nooranadu, Chunakkara, Palamel Thamarakkulam Panchayaths and providing FHTC |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-Augmentation of ARWSS to Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths -Renovation to 10 mld WTP Pattoor, Supplying and Laying of Distribution lines and giving House connections in Nooranadu, Chunakkara, Palamel Thamarakkulam Panchayaths and providing FHTC |
Status | On-going |
District | Alappuzha |
Executing Office | Alappuzha Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 526200000 |
TS Number | TS/2020-2021/2020/21524 |
Technical specification | JJM-Augmentation of ARWSS to Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths -Renovation to 10 mld WTP Pattoor, Supplying and Laying of Distribution lines and giving House connections in Nooranadu, Chunakkara, Palamel Thamarakkulam Panchayaths and providing FHTC |
Contractor | M/s. Tomco Engineering (P) Ltd (Mob: 9447082222) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 11/06/2021 |
---|---|
Scheduled date of Completion as per agreement | 10 Feb 2022 |
Expected date of Completion | 31/05/2022 |
TS Date | 21 Oct 2020 |
---|---|
Estimate Approval | 21 Oct 2020 |
NIT Approval | 02 Nov 2020 |
Tender Closing | 06 Nov 2020 |
Technichal Pre-Qualification | 10 Nov 2020 |
Price bid opening | 27 Oct 2020 |
Workorder Date | 22 Dec 2020 |
---|---|
NA | 11 Feb 2021 |
Alappuzha Project Dn PM |
Date: 29/06/2024 |
Work in progress | 97% Completed
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 12502 FHTCs done, Out of 163 km of laying completed in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths. .
Alappuzha Project Dn PM |
Date: 28/06/2024 |
Work in progress | 97% Completed
Construction of Pattoor OHSR, Nooranadu completed, Out of 23000 FHTCs, around 12502 FHTCs done, Out of 163 km of laying completed in Nooranad, Chunakkara, Palamel and Thamarakulam Panchayaths. .