Project | Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Punnappra South Panchayath and allied works |
---|---|
Project Code | ALPJJM09204256P1 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Punnappra South Panchayath and allied works |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Punnappra South Panchayath and allied works |
Status | On-going |
District | Alappuzha |
Executing Office | Alappuzha PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 44390000 |
TS Number | TS/2020-2021/2020/15340 |
Technical specification | Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Punnappra South Panchayath and allied works |
Contractor | Praveenkumar.V (Mob: 9846969824) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 03/11/2020 |
---|---|
Scheduled date of Completion as per agreement | 31 Mar 2021 |
Expected date of Completion | 31/01/2022 |
TS Date | 29 Aug 2020 |
---|---|
Estimate Approval | 29 Aug 2020 |
NIT Approval | 04 Sep 2020 |
Tender Closing | 17 Sep 2020 |
Technichal Pre-Qualification | 28 Sep 2020 |
Price bid opening | 19 Sep 2020 |
Workorder Date | 29 Sep 2020 |
---|---|
NA | 14 Oct 2020 |
Alappuzha PH Sn AE |
Date: 18/10/2023 |
Work in progress | 99% Completed
PWD & NH Road cutting Sanction awaiting ( Near Fish Land - 3 Places, ROW NO. 1048569 (Old) ROW NO. 1063780 (New). Joint verification completed. .
Alappuzha PH Dn EE |
Date: 20/06/2023 |
Work in progress | 99% Completed
PWD & NH Road cutting Sanction awaiting ( Near Fish Land - 3 Places, ROW NO. 1048569 (Old) ROW NO. 1063780 (New)..