Project | Construction of 12m dia intake well at Njankadavu SAAP YEAR 2017-18 |
---|---|
Project Code | KLMGOI0917464P3 |
Type | Package |
Main Project | 22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-AMRUT-Augmentation of WSS in Kollam Corporation(8518) |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | Construction of 12m dia intake well at Njankadavu |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 19270000 |
TS Number | TS/271/2017-18 |
Technical specification | 12 M DIA INTAKE WELL 16M DEPTH |
Contractor | PAILY ABRAHAM (Mob: 9847551289) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/04/2018 |
---|---|
Scheduled date of Completion as per agreement | 04 Oct 2019 |
Expected date of Completion | 15/02/2020 |
TS Date | 22 Dec 2017 |
---|---|
Estimate Approval | 22 Nov 2017 |
NIT Approval | 22 Nov 2017 |
Tender Closing | 12 Feb 2018 |
Technichal Pre-Qualification | 12 Feb 2018 |
Price bid opening | 05 Mar 2018 |
NA | 04 Apr 2018 |
---|---|
Workorder Date | 19 Mar 2018 |
Kollam Project HD |
Date: 01/06/2022 |
Work has been completed | 100% Completed
Work completed on 15/02/2020.
Kollam Project HD |
Date: 14/12/2021 |
Work has been completed | 100% Completed
Work completed .