- Home
- KIIFB-Augmentation and Modernization of...
KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package III
Project |
KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package III |
Project Code |
ALPKIIFB0619496P1 |
Type |
Package |
Main Project |
KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths
|
Funding Agency |
KIIFB |
Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Construction of 9LL OHSR at Vyasapuram of Aryad Pt ,12LL OHSR and 3 LL Sump cum pump house at FHC Kalavoor of Mannancherry Pt ,Laying clear water pumping main Ramavarma to OHSR at Vyasapuram 280mm HDPE 500m,Laying clear water pumping main from Mandhankaval to OHSR at FHC Kalavoor 315mm HDPE 6500m,Supplying and laying distribution system Mararikkulam Pt zone 1 and 2, Supplying and laying distribution system Aryad Pt zone 1, Supplying and laying distribution system Mannancherry Pt zone 1 &2,30 Hp CF pump sets 4 Nos |
Status |
On-going |
District |
Alappuzha |
Executing Office |
KIIFB Projects (ALP) |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
403100000 |
TS Number |
WRD/KWA-CEP/EST_TS/107/2022_5_1 |
Technical specification |
Construction of 9LL OHSR at Vyasapuram of Aryad Pt ,12LL OHSR and 3 LL Sump cum pump house at FHC Kalavoor of Mannancherry Pt ,Laying clear water pumping main Ramavarma to OHSR at Vyasapuram 280mm HDPE 500m,Laying clear water pumping main from Mandhankaval to OHSR at FHC Kalavoor 315mm HDPE 6500m,Supplying and laying distribution system Mararikkulam Pt zone 1 and 2, Supplying and laying distribution system Aryad Pt zone 1, Supplying and laying distribution system Mannancherry Pt zone 1 &2,30 Hp CF pump sets 4 Nos |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
25 Oct 2021 |
Pending |
Pending |
Road Cut Related Risk |
Joint Inspection conducted with PWD for getting estimates for Road Restoration works.PWD has rejected all applications citing that all the roads are under DLP |
No comments available. |
Pending |
27 Sep 2021 |
Pending |
Pending |
Land Related Risk |
Land for construction of 9LL OHSR at Vyasapuram in Aryad panchayath and 12LL OHSR at Kalavoor in Mannancherry panchayath have to be transferred to KWA from Scheduled Tribe department and Kerala State Housing Board respectively |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
Date is not specified |
Scheduled date of Completion as per agreement |
Date is not specified |
Expected date of Completion |
31/12/2023 |
Processing Dates
TS Date |
12 Aug 2022 |
Estimate Approval |
12 Aug 2022 |
NIT Approval |
17 Aug 2022 |
Tender Closing |
01 Nov 2022 |
Technichal Pre-Qualification |
03 Nov 2022 |
Price bid opening |
05 Nov 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Alappuzha KIIFB - AE 4 |
Date: 17/05/2024 |
Work has started | 0% Completed
Single offer received on tender . Awaiting approval of pre qualification. Tender committee disqualify the bidder, so retender process in progress. Now thee work retendered with due date 01-10-2023.Since no offer received. Retendered extended up to 30.10.2023.No offer received. Retender work is in progress. Due date 4.12.2023.No offer Received. Retendered with last date 07.01.2024.No offer received. Retendered with due date 24.01.2024.No offer received. Retendered with due date 19.02.2024. Date extended to 04.03.2024. No offer received. Date extended to 11.03.2024. No offer received . Date extended to 21.03.2024. No offer received. Date extended to 01.04.2024. No offer received. Date extended to 15.04.2024. No offer received. Date extended to 02.05.2024. No offer received . Date extended to 24.05.2024..
Alappuzha KIIFB - AE 4 |
Date: 16/05/2024 |
Work has started | 0% Completed
Single offer received on tender . Awaiting approval of pre qualification. Tender committee disqualify the bidder, so retender process in progress. Now thee work retendered with due date 01-10-2023.Since no offer received. Retendered extended up to 30.10.2023.No offer received. Retender work is in progress. Due date 4.12.2023.No offer Received. Retendered with last date 07.01.2024.No offer received. Retendered with due date 24.01.2024.No offer received. Retendered with due date 19.02.2024. Date extended to 04.03.2024. No offer received. Date extended to 11.03.2024. No offer received . Date extended to 21.03.2024. No offer received. Date extended to 01.04.2024. No offer received. Date extended to 15.04.2024. No offer received. Date extended to 02.05.2024. No offer received . Date extended to 24.05.2024..