| Project | DEPOSIT-RWSS to Sooranad South-Providing water Connection to Common Facility Centre at Sooranad South.-General Civil Work |
|---|---|
| Project Code | KLMDEPO062417004P1 |
| Type | Package |
| Main Project | DEPOSIT-RWSS to Sooranad South-Providing water Connection to Common Facility Centre at Sooranad South.-General Civil Work |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | DEPOSIT-RWSS to Sooranad South-Providing water Connection to Common Facility Centre at Sooranad South.-General Civil Work |
| Status | On-going |
| District | Kollam |
| Executing Office | Sasthamcottah WS Sn1 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | |
| TS Number | |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | Date is not specified |
| Sasthamcotta WS Sn 1 - AE |
| Date: 05/02/2025 |
Work has been completed | 100% Completed
Work 100 % completed on 02.02.2025 , bill preparation under progress..
| Sasthamcotta WS Sn 1 - AE |
| Date: 04/02/2025 |
Work in progress | 99% Completed
Work completed. Bill under preparation.