Jal Jeevan Mission (JJM)-Jal Jeevan Mission-WSS to Anjarakkandy, Peralassery and adjoining Pt.-Water supply arrangements to Theeradesam in Muzhappilangad Pt-Laying Distribution systems and providing FHTCS-Balance work-Pipeline Work
Project |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission-WSS to Anjarakkandy, Peralassery and adjoining Pt.-Water supply arrangements to Theeradesam in Muzhappilangad Pt-Laying Distribution systems and providing FHTCS-Balance work-Pipeline Work |
Project Code |
KNRJJM082015404 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission-WSS to Anjarakkandy, Peralassery and adjoining Pt.-Water supply arrangements to Theeradesam in Muzhappilangad Pt-Laying Distribution systems and providing FHTCS-Balance work-Pipeline Work |
Status |
On-going |
District |
Kannur |
Executing Office |
Kannur WS Dn |
AS Amount (Rs) |
51410000
|
AS Number |
G.O.(Rt)No.541/2020/WRD |
TS Amount (Rs) |
10500000 |
TS Number |
22404/2023-2024 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
46.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission-WSS to Anjarakkandy, Peralassery and adjoining Pt.-Water supply arrangements to Theeradesam in Muzhappilangad Pt-Laying Distribution systems and providing FHTCS-Balance work-Pipeline Work |
Perlassery Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Jun 2024 |
95% work completed.5165m pipe laid.61nos. FHTC provided |
Perlassery Sn 2 AE |
|
20 Jun 2024 |
95% work completed.5165m pipe laid.61nos. FHTC provided |
Perlassery Sn 2 AE |
|
10 Jun 2024 |
95% work completed.5165m pipe laid.61nos. FHTC provided |
Perlassery Sn 2 AE |
|
01 Jun 2024 |
95% work completed.5165m pipe laid.61nos. FHTC provided |
Perlassery Sn 2 AE |
|
22 May 2024 |
95% work completed.5165m pipe laid.61nos. FHTC provided |
Perlassery Sn 2 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
20/12/2023 |
Scheduled date of Completion of the Project |
20 Mar 2024 |
Expected date of Completion |
20/03/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
20 Dec 2023 |