Deposit work: Water supply improvements to mynagappally grama panchayath - Restoration of PWD road from WTP Sasthamcotta to mynagappally - KIIFB 2016-17- ANJILIMOOD - MYNAGAPPALLY SASTHAMCOTTA ROAD IN KOLLAM DISTRICT

Project Deposit work: Water supply improvements to mynagappally grama panchayath - Restoration of PWD road from WTP Sasthamcotta to mynagappally - KIIFB 2016-17- ANJILIMOOD - MYNAGAPPALLY SASTHAMCOTTA ROAD IN KOLLAM DISTRICT
Project Code KLMDC-LAC/ADS/SDF/KSCADC09205385P3
Type Package
Main Project Deposit work Mynagappally Grama Panchayath Phase 1 Water supply improvements to Mynagappally Panchayath Supplying and Laying 300mm DI K9 pipe from WTP at Sasthamcotta towards Mynagappally for the length of 840mts Chainage from 0.00m to 840.00m.
Funding Agency DC-LAC/ADS/SDF/KSCADC
Category Deposit Work
Type of scheme Water Supply
Scheme DC-LAC/ADS/SDF/KSCADC
Description Deposit work: Water supply improvements to mynagappally grama panchayath - Restoration of PWD road from WTP Sasthamcotta to mynagappally - KIIFB 2016-17- ANJILIMOOD - MYNAGAPPALLY SASTHAMCOTTA ROAD IN KOLLAM DISTRICT
Status Completed
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 1102671
TS Number TS/2020-2021/2020/25142
Technical specification PWD Road Restoration

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 06/11/2020
Scheduled date of Completion as per agreement 03 Feb 2022
Expected date of Completion 03/02/2022

Processing Dates

TS Date 28 Oct 2020
Estimate Approval 28 Oct 2020
NIT Approval 28 Oct 2020
Tender Closing 06 Nov 2020
Technichal Pre-Qualification 09 Nov 2020
Price bid opening 09 Nov 2020

Approval Dates

Workorder Date 03 Jan 2021
NA 04 Jan 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 18/02/2022

Work has been completed | 100% Completed