| Project | State Plan-STATE PLAN 2023-24 :Setting up of Laboratory Waste Water Treatment Facility at Quality Control Sub District Lab Sasthamcotta-Waste Water Treatment |
|---|---|
| Project Code | KLMGOK082316742P1 |
| Type | Package |
| Main Project | State Plan - 2023-24 - Setting up of Waste Water Treatment Facility in Quality Control District and Sub District Laboratories under QC Division, Thiruvanathapuram - Kollam District |
| Funding Agency | GOK |
| Category | State plan |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | Setting up of Waste water treatment facility at Quality Control Sub District Lab Sasthamcotta to filter and reuse the waste water from the chemical laboratory for non potable purpose |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam QC Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 6940000 |
| TS Number | WRD/KWA-CE(CR)/EST_TS/23313/2023_5_1_1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 18/07/2024 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 30/11/2024 |
| TS Date | 18 Jul 2024 |
|---|---|
| Estimate Approval | 18 Jul 2024 |
| Kollam QC AE |
| Date: 09/01/2026 |
Work has started | 0% Completed
Work tendered no bid retendered once and no bid received , work dropped.
| Kollam QC AE |
| Date: 28/06/2025 |
Work has started | 0% Completed
Work retendered once and no bid received yet to be retendered .